Latest start time

  • Saul I. Gass
  • Carl M. Harris
Reference work entry
DOI: https://doi.org/10.1007/1-4020-0611-X_520

The latest time an activity can start without delaying the end of a project. A delay of an activity beyond the latest start time will delay the entire project completion by a corresponding amount. These times are calculated on the basis of a “reverse pass” through the network.  Network planning.