Latest finish time
Reference work entry
First Online:
DOI: https://doi.org/10.1007/1-4020-0611-X_519
- 15 Downloads
The latest time an activity must be completed without delaying the end of a project. It is simply the sum of the latest start time of the activity and its duration. Network planning.