(1) The nature and extent of the work to be executed shall be set out in the contract. The “General technical specifications in construction contracts (ATV)” also form part of the contract.
(2) In the event of inconsistencies in the contract, its separate parts shall take precedence in the following order:
1. the specification of works,
2. the special conditions of contract,
3. any supplementary conditions of contract,
4. any supplementary technical specifications,
5. the “General technical specifications in construction contracts” (DIN 18299),
6. the general conditions of contract relating to the execution of construction work.
(3) The client has the right to order alterations to the design.
(4) Work which, though not included in the original contract, is found to be necessary for its completion, shall also be carried out by the contractor at the client’s request unless the contractor’s business is not equipped for the purpose. Other work may only be allocated to a contractor with its consent.
Access this chapter
Tax calculation will be finalised at checkout
Purchases are for personal use only
Preview
Unable to display preview. Download preview PDF.
Author information
Authors and Affiliations
Consortia
Editor information
Editors and Affiliations
Rights and permissions
Copyright information
© 2014 Springer Fachmedien Wiesbaden
About this chapter
Cite this chapter
Springer Fachmedien Wiesbaden. (2014). Part B: General conditions of contract relating to the execution of construction work 2012 edition. In: VOB/B 2012 - Textausgabe/Text Edition. Springer Vieweg, Wiesbaden. https://doi.org/10.1007/978-3-658-05222-5_2
Download citation
DOI: https://doi.org/10.1007/978-3-658-05222-5_2
Published:
Publisher Name: Springer Vieweg, Wiesbaden
Print ISBN: 978-3-658-05221-8
Online ISBN: 978-3-658-05222-5
eBook Packages: Computer Science and Engineering (German Language)