In March 2006, HM Treasury set out its updated approach to Private Finance Initiatives (PFI) in the document PFI: Strengthening Long-Term Partnerships (HM Treasury, 2006a). This document, building on the measures introduced since 2003, set out further improvements to PFI to support its ongoing role in delivering better public services. These recent approaches include:
-
Measures based on the government’s research to build on the operational and contractual flexibility under PFI, including increased support to public sector managers during this phase of the contract.
-
Measures further to improve the ability of the public sector to understand where PFI is likely to offer better value for money (VfM) than other procurement routes. This will be achieved by assisting procuring authorities in understanding the VfM of key decisions within a project including strengthening the test for the inclusion of soft services.
-
Measures to bolster the professionalism of PFI procurement to reduce procurement times. While procurement is improving, the government believes that procurement times remain unnecessarily long and is introducing steps to improve the maturity of projects before they are tendered into the market, to reduce unnecessary uncertainty later in the procurement.
-
Measures to support local decision-making in PH through the provision of central skills and capabilities to ensure approvals are given at the right points in the process.
This chapter is based largely on HM Treasury (2006a), HM Treasury, Crown Copyright.
Access this chapter
Tax calculation will be finalised at checkout
Purchases are for personal use only
Preview
Unable to display preview. Download preview PDF.
References
HM Treasury, 2003, PFI: Meeting the Investment Challenge (London). Available via the Internet: http://www.hm-treasury.gov.uk/documents/enterprise_and_productivity/PFI.cfm.
HM Treasury, 2006a, PFI: Strengthening Long-Term Partnerships (London). Available via the Internet: http://www.hm-treasury.gov.uk/budget/budget_06/other_documents/bud_bud06_odpfi.cfm.
HM Treasury, 2006b, Value for Money Assessment Guidance (London). Available via the Internet: http://www.hm-treasury.gov.uk/documents/public_private_partnerships/additional_guidance/ppp_vfm_index.cfm.
HM Treasury, 2007, Transforming Government Procurement (London). Available via the Internet: http://www.hm-treasury.gov.uk/media/E/6/government_procurement_pu147.pdf.
HM Treasury, 2008, Infrastructure Procurement: Delivering Long-Term Value (London). Available via the Internet: http://www.hm-treasury.gov.uk/budget_08/documents/bud_bud08_procurement.cfm.
KPMG/BSA, 2005, Effectiveness of Operational Contracts in PFI (UK). Available via the Internet: http://www.kpmg.co.uk/email/iandg/pfireport.pdf.
Partnerships UK, 2006, Report on Operational PFI projects (London). Available via the Internet: http://www.partnershipsuk.org.uk/newsAttachments/documents/doc_70_22–3-200613–58-41.pdf
Editor information
Editors and Affiliations
Copyright information
© 2008 International Monetary Fund
About this chapter
Cite this chapter
Farquharson, E. (2008). Managing PFI Projects in the United Kingdom. In: Schwartz, G., Corbacho, A., Funke, K. (eds) Public Investment and Public-Private Partnerships. Procyclicality of Financial Systems in Asia. Palgrave Macmillan, London. https://doi.org/10.1057/9780230593992_12
Download citation
DOI: https://doi.org/10.1057/9780230593992_12
Publisher Name: Palgrave Macmillan, London
Print ISBN: 978-1-349-29944-7
Online ISBN: 978-0-230-59399-2
eBook Packages: Palgrave Economics & Finance CollectionEconomics and Finance (R0)