Onsite Technical and Economic Performance Evaluation of PWT (Pipeline Welding Technology): A Comparative Analysis with CRC-Evans Welding Technology

  • Anubhav RawatEmail author
  • Bhagwat Singh Shishodia
Conference paper
  • 458 Downloads
Part of the Lecture Notes in Mechanical Engineering book series (LNME)

Abstract

During cross-country underground pipeline construction welding is one of the major construction activity. At various parts of the world, many pipeline welding machines are in use to produce defect-free economic pipeline joints. Every weld machine manufacturer claims its own advantages and other’s drawbacks. Two famous welding machine manufacturing companies for pipelines are PWT (Italy) and CRC-Evans (USA). Thus, the current work at the cross-country gas pipeline construction site from Vijaypur (MP, India) to Dadri (UP, India) (VDPL) is taken up to determine which of the above two mentioned machines are technically better and relatively cheaper while determining weld joint cost and overall pipeline construction cost. Data of two construction sites of VDPL namely Guna and Mathura are collected for weld joint construction and repair. The sites were constructed by ESSAR and EIL for GAIL. The carbon steel pipeline being laid was of 48” nominal size. A detailed cost analysis of the machines is estimated by considering all the related man, machine and material cost, both for mainline weld and weld joint repair. Technical performance of the weld machines is evaluated by comparing various weld parameters for pipeline weld joints. Performance of both of the machines is found to be comparable and almost equal in terms of total cost involved but the repair cost of PWT is less than CRC. Both PWT and CRC are found to produce weld defects with defect of incomplete fusion (IF) more frequently. Suitable remedies are suggested for improvement.

Keywords

Pipeline Construction Pipeline welding technology Weld defects Incomplete fusion (IF) Weld construction cost 

Notes

Acknowledgements

The authors are thankful to Essar Construction India Limited (ECIL), for allowing to work on their construction sites and providing access to all the necessary documents and information.

References

  1. 1.
    Kim IS, Jeong YJ, Lee CW, Yarlagadda PK (2003) Prediction of welding parameters for pipeline welding using an intelligent system. Int J Advanc Manufact Technol 22(9–10):713–719CrossRefGoogle Scholar
  2. 2.
    Yapp D, Blackman SA (2004) Recent developments in high productivity pipeline welding. J Brazilian Soc Mech Sci Eng 26(1):89–97CrossRefGoogle Scholar
  3. 3.
    McAllister EW (2013) Pipeline rules of thumb handbook: a manual of quick, accurate solutions to everyday pipeline engineering problems. Gulf Professional PublishingGoogle Scholar
  4. 4.
    Vaidya V, Viwek V, Christopher C, Chasse L (2000) Methods and apparatus for welding performance measurement. U.S. Patent 6,051,805, issued April 18, 2000Google Scholar
  5. 5.
    Geisler R (2012) ‘Estimating total welding costs’Google Scholar
  6. 6.
    Gordon R, Holdren R, Johnson M, Lozev M (2003) Reducing pipeline construction costs: New technologies. Welding World 47(5–6):7–14CrossRefGoogle Scholar
  7. 7.
    Marco B ‘Technical calculation and estimators man hour manual’Google Scholar
  8. 8.
  9. 9.
    Essar projects, construction manualsGoogle Scholar
  10. 10.
    Anubhav R (2010) ‘Welding stress and defect analysis of oil and gas pipelines’ M. Tech. Thesis, University of Petroleum and Energy Studies, Dehradun, IndiaGoogle Scholar

Copyright information

© Springer Nature Singapore Pte Ltd. 2019

Authors and Affiliations

  1. 1.Department of Mechanical EngineeringBen Gurion University of the NegevBeershebaIsrael
  2. 2.Department of Mechanical EngineeringJIETJodhpurIndia

Personalised recommendations