Plant Cost Estimates

  • Chapter
Chemical Engineering Economics

Abstract

Once individual equipment costs are known from either manufacturers’ price quotations or estimating charts as discussed in the previous chapter, they can be utilized to form preliminary total plant cost estimates. A suggested sequence for obtaining such estimates is as follows:

  1. 1.

    Prepare a flow sheet for the process or operation to be estimated, showing all of the major equipment and whatever of the basic auxiliary or general plant facilities that directly affect the process (i.e., boilers for steam; cooling towers; special electric requirements, unusual storage facilities, transportation equipment, etc.).

  2. 2.

    Prepare heat and material balances around each piece of equipment to the degree of accuracy and detail required to size the equipment.

  3. 3.

    Size all of the equipment with the precision required to obtain the parameters needed for manufacturers’ cost quotations or to estimate costs from charts.

  4. 4.

    Analyze the process carefully to determine what “plant cost factors” should be used, and then prepare a detailed breakdown of the total plant cost package. This will be discussed in the following sections.

This is a preview of subscription content, log in via an institution to check access.

Access this chapter

eBook
USD 16.99
Price excludes VAT (USA)
  • Available as PDF
  • Read on any device
  • Instant download
  • Own it forever
Softcover Book
USD 129.99
Price excludes VAT (USA)
  • Compact, lightweight edition
  • Dispatched in 3 to 5 business days
  • Free shipping worldwide - see info

Tax calculation will be finalised at checkout

Purchases are for personal use only

Institutional subscriptions

Preview

Unable to display preview. Download preview PDF.

Unable to display preview. Download preview PDF.

References

  • Bridgwater, A. V. 1979. International construction cost location factors. Chemical Engineering (Nov. 5).

    Google Scholar 

  • Brooks, Kenneth. 1988. A suite of software to aid plant engineers. Chemical Week (March 2):32–35.

    Google Scholar 

  • Chemical Engineering. 1974. Sources and Production Economics of Chemical Products. McGraw-Hill, New York:121–180

    Google Scholar 

  • Chilton, C. H. 1960. Cost Engineering in the Process Industries. McGraw-Hill, New York.

    Google Scholar 

  • Cran, John. 1981. Improved factored method gives better preliminary cost estimates. Chemical Engineering (April 6):65–79.

    Google Scholar 

  • Guthrie, Kenneth M. 1970. Capital and operating costs for 54 chemical processes. Chemical Engineering (June 15):140–156.

    Google Scholar 

  • Guthrie, Kenneth M. 1974. Process Plant Estimating, Evaluation and Control. Craftsman Book Co., Solana Beach, CA:125–180; 334–353; 369–371.

    Google Scholar 

  • Holland, F.A., F.A. Watson, and J. K. Wilkinson. 1974. Introduction to Process Economics. John Wiley & Sons, London:1–346.

    Google Scholar 

  • Kharbanda, O. P. 1979. Process Plant and Equipment Cost Estimation. Craftsman Book Co., Solana Beach, CA:213–225.

    Google Scholar 

  • Klumpar, Ivan V., and Steven T. Slaysky 1985a. Updated cost factors: Process equipment. Chemical Engineering (July 22):73.

    Google Scholar 

  • Klumpar, Ivan V., 1985b. Commodity materials. Chemical Engineering (Aug. 19):76–77.

    Google Scholar 

  • Klumpar, Ivan V., 1985c. Installation labor. Chemical Engineering (Sept. 16):85–87.

    Google Scholar 

  • Lang, H. J. 1947. Cost data correlated. Chemical Engineering (Sept.):130–133.

    Google Scholar 

  • Liptak, B. G. 1970. Cost of process instruments. Chemical Engineering (Sept).

    Google Scholar 

  • Mendel, Otto 1985. Estimating engineering cost. Chemical Engineering (Dec. 9 & 23):117–118.

    Google Scholar 

  • Parkinson, Gerald 1987. New study provides clues to project-cost overruns. Chemical Engineering (Aug. 17):33–37.

    Google Scholar 

  • Viola, J. L., Jr. 1981. Estimate capital costs via a new shortcut method. Chemical Engineering (April 16):80–86.

    Google Scholar 

  • Ward, Thomas J. 1984. Predesign estimates of plant capital cost. Chemical Engineering (Sept. 17):121–124.

    Google Scholar 

  • Ward, Thomas J. 1986. Cost estimating methods. American Institute of Chemical Engineers Modular Instruction Series, Plant Design and Cost Estimating, Vol. 1:12–21.

    Google Scholar 

Download references

Author information

Authors and Affiliations

Authors

Rights and permissions

Reprints and permissions

Copyright information

© 1989 Van Nostrand Reinhold

About this chapter

Cite this chapter

Garrett, D.E. (1989). Plant Cost Estimates. In: Chemical Engineering Economics. Springer, Dordrecht. https://doi.org/10.1007/978-94-011-6544-0_3

Download citation

  • DOI: https://doi.org/10.1007/978-94-011-6544-0_3

  • Publisher Name: Springer, Dordrecht

  • Print ISBN: 978-94-011-6546-4

  • Online ISBN: 978-94-011-6544-0

  • eBook Packages: Springer Book Archive

Publish with us

Policies and ethics