Abstract

As already mentioned in Chap. 1, the preparatory investigation, design and construction of the Honshu-Shikoku Bridges (HSB) had 40 years of history as shown in Table 3.1, and its construction finally came to the end by completing the Akashi-Kaikyo Bridge in 1998 and the Tatara Bridge as well as Kurushima-Kaikyo Bridges in 1999.

Keywords

Wind Tunnel Bridge Deck Wind Load Wind Tunnel Test Suspension Bridge 