Project Scheduling with Discounted Cash Flows and General Temporal Constraints

  • Conference paper
Operations Research Proceedings 1999

Part of the book series: Operations Research Proceedings 1999 ((ORP,volume 1999))

Abstract

The net present value is widely regarded as the main financial criterion for evaluating the return on assets and profitability of large scaled projects. Considering activity-on-arc networks, the positive and negative cash flows that occur throughout the project lifetime are associated with the completion of activities. Emphasizing the financial aspects of project management, the activities of the project have to be scheduled such that the net present value of the project is maximized and all temporal and resource constraints are met. For solving the resource unconstrained case, we consider an exact solution procedure based on a first-order steepest ascent approach where the ascent direction is normalized by the supremum norm. Using the concept of minimal delaying modes, we device a branch-and-bound procedure for solving the resource-constrained project scheduling problem with discounted cash flows where we use a dual method to solve the resource relaxation in each node of the enumeration tree. To speed up the procedure preprocessing, immediate selection and a generalized subset dominance rule are used. An experimental performance analysis shows that the proposed algorithms clearly outperforms the procedures proposed in the open literature.

This is a preview of subscription content, log in via an institution to check access.

Access this chapter

Chapter
USD 29.95
Price excludes VAT (USA)
  • Available as PDF
  • Read on any device
  • Instant download
  • Own it forever
eBook
USD 99.00
Price excludes VAT (USA)
  • Available as PDF
  • Read on any device
  • Instant download
  • Own it forever
Softcover Book
USD 132.00
Price excludes VAT (USA)
  • Compact, lightweight edition
  • Dispatched in 3 to 5 business days
  • Free shipping worldwide - see info

Tax calculation will be finalised at checkout

Purchases are for personal use only

Institutional subscriptions

Preview

Unable to display preview. Download preview PDF.

Unable to display preview. Download preview PDF.

Similar content being viewed by others

References

  1. Bartusch M., Möhring R.H., Radermacher F.J. (1988): Scheduling project networks with resource constraints and time windows, Annals of Operations Research 16, 201–240.

    Article  Google Scholar 

  2. De Reyck B. (1998): Scheduling projects with generalized precedence relations: exact and heuristic procedures, Ph. D. Dissertation, Catholic University of Leuven.

    Google Scholar 

  3. De Reyck B., Herroelen W. (1998): An optimal procedure for the resource-constrained project scheduling problem with discounted cash flows and generalized precedence relations, Computers and Operations Research 25, 1–17.

    Article  Google Scholar 

  4. Herroelen W.S., Van Dommelen P., Demeulemeester E.L. (1997): Project network models with discounted cash flows: a guided tour through recent developments, European Journal of Operational Research 100, 97–121.

    Article  Google Scholar 

  5. Grinold R.C. (1972): The payment scheduling problem, Naval Research Logistics Quarterly 19, 123–136.

    Article  Google Scholar 

  6. Kamburowski J. (1990): Maximizing the project net present value in activity networks under generalized precedence relations, Proceedings of 21st DSI Annual Meeting, San Diego, 748–750.

    Google Scholar 

  7. Neumann K., Zimmermann J. (1998): Exact and heuristic procedures for net present value and resource levelling problems in project scheduling, Technical Report WIOR-538, University of Karlsruhe, submitted to European Journal of Operational Research.

    Google Scholar 

  8. Schwindt C. (1998): Generation of resource-constrained project scheduling problems subject to temporal constraints, Technical Report WIOR-543, University of Karlsruhe, submitted to European Journal of Operational Research.

    Google Scholar 

  9. Schwindt C., Zimmermann J. (1998): Maximizing the net present value of projects subject to temporal constraints, Technical Report WIOR-536, University of Karlsruhe.

    Google Scholar 

Download references

Author information

Authors and Affiliations

Authors

Editor information

Editors and Affiliations

Rights and permissions

Reprints and permissions

Copyright information

© 2000 Springer-Verlag Berlin Heidelberg

About this paper

Cite this paper

Zimmermann, J. (2000). Project Scheduling with Discounted Cash Flows and General Temporal Constraints. In: Inderfurth, K., Schwödiauer, G., Domschke, W., Juhnke, F., Kleinschmidt, P., Wäscher, G. (eds) Operations Research Proceedings 1999. Operations Research Proceedings 1999, vol 1999. Springer, Berlin, Heidelberg. https://doi.org/10.1007/978-3-642-58300-1_65

Download citation

  • DOI: https://doi.org/10.1007/978-3-642-58300-1_65

  • Publisher Name: Springer, Berlin, Heidelberg

  • Print ISBN: 978-3-540-67094-0

  • Online ISBN: 978-3-642-58300-1

  • eBook Packages: Springer Book Archive

Publish with us

Policies and ethics