Earned Value Management

  • Chapter
  • First Online:
Project Management with Dynamic Scheduling

Abstract

In the previous parts of this book, it was assumed that the project has not started yet, and hence, the project was still in the definition and scheduling phase of the project life cycle. From this chapter on, it is assumed that the project has started (execution phase) and that the project is in progress. Consequently, it is the task of the project manager to carefully control the performance of the project, using his/her knowledge of the schedule risk analyses and baseline scheduling steps discussed in the two previous parts. The project control dimension of dynamic scheduling can be done relying on a well-established technique known as Earned Value Management.Earned Value Management (EVM) is a methodology used since the 1960s, when the USA department of defense proposed a standard method to measure a project’s performance. The system relies on a set of often straightforward metrics to measure and evaluate the general health of a project. These metrics serve as early warning signals to timely detect project problems or to exploit project opportunities. The purpose of an EVM system is to provide answers to project managers on questions such as:

  • What is the difference between budgeted and actual costs?

  • What is the current project status? Ahead of schedule or schedule delay?

  • Given the current project performance, what is the expected remaining time and cost of the project?

This chapter gives an overview of all EVM metrics and performance measures to monitor the time and cost dimension of a project’s current progress to date, and shows how this information can be used to predict the expected remaining time and cost to finalize the project. This information serves as a trigger to take corrective actions to bring the project back on track when needed.

This is a preview of subscription content, log in via an institution to check access.

Access this chapter

Chapter
USD 29.95
Price excludes VAT (USA)
  • Available as PDF
  • Read on any device
  • Instant download
  • Own it forever
eBook
USD 149.00
Price excludes VAT (USA)
  • Available as EPUB and PDF
  • Read on any device
  • Instant download
  • Own it forever
Softcover Book
USD 199.99
Price excludes VAT (USA)
  • Compact, lightweight edition
  • Dispatched in 3 to 5 business days
  • Free shipping worldwide - see info
Hardcover Book
USD 199.99
Price excludes VAT (USA)
  • Durable hardcover edition
  • Dispatched in 3 to 5 business days
  • Free shipping worldwide - see info

Tax calculation will be finalised at checkout

Purchases are for personal use only

Institutional subscriptions

Notes

  1. 1.

    Excluding situations where projects are on time and/or on budget.

References

  • Anbari F (2003) Earned value project management method and extensions. Proj Manag J 34(4): 12–23

    Google Scholar 

  • Book S (2006a) Correction note: “earned schedule” and its possible unreliability as an indicator. The Measurable News Fall:22–24

    Google Scholar 

  • Book S (2006b) “Earned schedule” and its possible unreliability as an indicator. The Measurable News Spring:24–30

    Google Scholar 

  • Christensen D (1993) The estimate at completion problem: a review of three studies. Proj Manag J 24:37–42

    Google Scholar 

  • Cooper K (2003) Your project’s real price tag? Letters to the editor. Harv Bus Rev 81:122–122

    Google Scholar 

  • Fleming Q, Koppelman J (2003) What’s your project’s real price tag? Harv Bus Rev 81:20–21

    Google Scholar 

  • Fleming Q, Koppelman J (2005) Earned value project management, 3rd edn. Project Management Institute, Newtown Square

    Google Scholar 

  • Jacob D (2003) Forecasting project schedule completion with earned value metrics. The Measurable News March:1, 7–9

    Google Scholar 

  • Jacob D (2006) Is “earned schedule” an unreliable indicator? The Measurable News Fall:15–21

    Google Scholar 

  • Jacob D, Kane M (2004) Forecasting schedule completion using earned value metrics? Revisited. The Measurable News Summer:1, 11–17

    Google Scholar 

  • Lipke W (2003) Schedule is different. The Measurable News Summer:31–34

    Google Scholar 

  • Lipke W (2006) Applying earned schedule to critical path analysis and more. The Measurable News Fall:26–30

    Google Scholar 

  • Lipke W, Zwikael O, Henderson K, Anbari F (2009) Prediction of project outcome: the application of statistical methods to earned value management and earned schedule performance indexes. Int J Proj Manage 27:400–407

    Article  Google Scholar 

  • Vandevoorde S, Vanhoucke M (2006) A comparison of different project duration forecasting methods using earned value metrics. Int J Proj Manag 24:289–302

    Article  Google Scholar 

  • Vanhoucke M (2010a) Measuring time - Improving project performance using earned value management, vol 136, International series in operations research and management science. Springer, New York

    Google Scholar 

Download references

Author information

Authors and Affiliations

Authors

Rights and permissions

Reprints and permissions

Copyright information

© 2013 Springer-Verlag Berlin Heidelberg

About this chapter

Cite this chapter

Vanhoucke, M. (2013). Earned Value Management. In: Project Management with Dynamic Scheduling. Springer, Berlin, Heidelberg. https://doi.org/10.1007/978-3-642-40438-2_12

Download citation

Publish with us

Policies and ethics