Construction Costs Estimate for Civil Works. A Model for the Analysis During the Preliminary Stage of the Project

  • Antonio NesticòEmail author
  • Gianluigi De Mare
  • Biagino Frusciante
  • Luigi Dolores
Conference paper
Part of the Lecture Notes in Computer Science book series (LNCS, volume 10408)

Abstract

In order to estimate the cost of construction it is necessary to identify all the elements having expense and to provide the corresponding economic values accordingly to the level of detail of the project. Given the high number of variables characterizing the engineering project, it is required to have simplified schemes able to facilitate the study and management of the project. In particular, a civil work needs to have a concise representation through a suitable classification system, which allows to identify sets of homogeneous elements such that the complexity of the analysis is reduced. The classification systems commonly treated in literature are indeed based on the assumption that the building process can be broken down into simple elements able to give an efficient representation of the whole project.

In the present paper, we first analyze the main classification systems of civil works, highlighting features, advantages and problems. Then, starting from the classification system proposed in Italy by the UNI 8290 regulation, which has been implemented and extended to multiple levels of detail, it is defined a Work Breakdown Structure (WBS) with the aim to be the reference for the description, the economic analysis and the management of the project already in the preliminary design stage and, later, also in its final planning stages and execution. Operationally, the decomposition of the project, aimed at identifying the processes needed to ensure the production of the work site, is the first step of the procedure, which is then followed by the quantification and the subsequent allocation of unit prices resulting from price lists. In these additional steps, we resort to semi-analytical estimation procedures, which allow us to draw up the Metric Computation (MC) and the Estimate Metric Computation (EMC) also in the preliminary design phase.

The use of a simplified base model for the decomposition of the project at the stage of preliminary analysis, can improve the accuracy of cost estimates, otherwise based on rough and often significantly approximate evaluations which follow from baseless estimates when compared to the macro-processing items. Increasing the accuracy of the cost estimates is of primarily interest as it can ensure higher margins of investments in the technical and economic feasibility of the project on the territory, which may cover the infrastructures, the urban planning, the implementation of new technologies for the environment and the rational use of the land. In this way, it is possible to reduce the risk associated to the project initiative, also allowing a unique decomposition scheme of the project. Such scheme, adopted since the preliminary study, can be then integrated through the following phases of the final and executive project.

Keywords

Cost estimate Planning levels UNI 8290 Uniformat II Standard form of cost analysis Work breakdown structure Quantity takeoff Bill of quantity 

References

  1. 1.
    Ashworth, A., Perera, S.: Cost Studies of Buildings. Routledge, London (2015)Google Scholar
  2. 2.
    Galli, D., Gentile, D., Gualandi, V.P.: Appalti Pubblici. IPSOA, Milano (2015)Google Scholar
  3. 3.
    Washington State Department of Transportation: Cost Estimating Manual for Project. WSDOT publications, USA (2015)Google Scholar
  4. 4.
    Oberlender, G.D.: Project Management for Engineering and Construction. McGraw-Hill, New York (1993)Google Scholar
  5. 5.
    AACE International: Recommended Practice No. 18R-97, Cost Estimate Classification System – as Applied for the Building and General Construction Industries. AACE International, USA (2011)Google Scholar
  6. 6.
    AACE International: Recommended Practice No. 56R-08, Cost Estimate Classification System – as Applied for the Building and General Construction Industries. AACE International, USA (2012)Google Scholar
  7. 7.
    Phaobunjong, K.: Parametric cost estimating model for conceptual cost estimating of building construction projects. Dissertation presented to the Faculty of the Graduate School of The University of Texas, Austin (2002)Google Scholar
  8. 8.
    Niazi, A., et al.: Product cost estimation: technique classification and methodology review. J. Manuf. Sci. Eng. 128(2), 563–575 (2006)CrossRefGoogle Scholar
  9. 9.
    USD (AT&L): Handbook: Construction Cost Estimating, Department of Defense, USA (2011)Google Scholar
  10. 10.
    Mislick, G.K., Nussbaum, D.A.: Cost estimation: methods and tools. Wiley, Hoboken (2015)CrossRefGoogle Scholar
  11. 11.
    De Mare, G., Morano, P.: La stima del costo delle opere pubbliche. Utet, Torino (2002)Google Scholar
  12. 12.
    Charette, R.P., Marshall, H.E.: UNIFORMAT II Elemental Classification for Building Specifications, Cost Estimating, and Cost Analysis. NIST, USA (1999)CrossRefGoogle Scholar
  13. 13.
    ASTM E 1557-97: Standard Classification for Building Elements and Related Sitework - UNIFORMAT II. American Society for Testing and Materials, West Conshohocken, PA (1997)Google Scholar
  14. 14.
    Akintoye, A., Fitzgerald, E.: A survey of current cost estimating practices in the UK. Constr. Manage. Econ. 18(2), 161–172 (2000)CrossRefGoogle Scholar
  15. 15.
    Benge, D.P.: NRM1 Cost Management Handbook. Routledge, London (2014)Google Scholar
  16. 16.
    Royal Institution of Chartered Surveyors: New Rules of Measurement. Order of Cost Estimating and Cost Planning for Capital Building Works. 2nd edn. RICS, Coventry, UK (2012)Google Scholar
  17. 17.
    Royal Institute of British Architects: RIBA Plan of Work 2013. RIBA, London (2013)Google Scholar
  18. 18.
    Building Costs Information Service: Elemental Standard Form of Cost Analysis, 4th edn. BCIS, London (2012)Google Scholar
  19. 19.
    Utica, G.: Ingegnerizzazione e gestione economica del progetto, vol. 1. Maggioli Editore, Rimini, Italy (2008)Google Scholar
  20. 20.
    Utica, G.: Tecniche avanzate di Analisi e gestione dei progetti. McGraw-Hill, Milano (2010)Google Scholar
  21. 21.
    Utica, G.: La stima sintetica del costo di costruzione, Il computo metrico e il computo metrico estimativo per classi di elementi tecnici. Maggioli Editore, Rimini, Italy (2011)Google Scholar
  22. 22.
    Tausworthe, R.C.: The work breakdown structure in software project management. J. Syst. Softw. 1, 181–186 (1980)CrossRefGoogle Scholar
  23. 23.
    Haugan, G.T.: Effective Work Breakdown Structures. Management Concepts Inc., Vienna, VA (2002)Google Scholar
  24. 24.
    Jung, Y., Woo, S.: Flexible work breakdown structure for integrated cost and schedule control. J. Constr. Eng. Manage. 130(5), 616–625 (2004)CrossRefGoogle Scholar
  25. 25.
    Miti, G.: Stima del costo di costruzione nelle opere di ingegneria civile, 2nd edn. Legislazione Tecnica, Roma (2016)Google Scholar
  26. 26.
    Nesticò, A., Pipolo, O.: A protocol for sustainable building interventions: financial analysis and environmental effects. Int. J. Bus. Intell. Data Min. 10(3), 199–212 (2015). doi: 10.1504/IJBIDM.2015.071325. Inderscience Enterprises Ltd., Genève, SwitzerlandCrossRefGoogle Scholar
  27. 27.
    Nesticò, A., Macchiaroli, M., Pipolo, O.: Costs and benefits in the recovery of historic buildings: the application of an economic model. Sustainability 7(11), 14661–14676 (2015). doi: 10.3390/su71114661. MDPI AG, Basel, SwitzerlandCrossRefGoogle Scholar
  28. 28.
    Bottero, M., Ferretti, V., Mondini, G.: How to support strategic decisions in territorial transformation processes. Int. J. Agric. Environ. Inf. Syst. 6(4), 40–55 (2015). doi: 10.4018/IJAEIS.2015100103. IGI Global Publishing, United StatesCrossRefGoogle Scholar
  29. 29.
    Morano, P., Tajani, F.: The break-even analysis applied to urban renewal investments: a model to evaluate the share of social housing financially sustainable for private investors. Habitat Int. 59, 10–20 (2017). doi: 10.1016/j.habitatint.2016.11.004 CrossRefGoogle Scholar
  30. 30.
    Kim, G.H., An, S.H., Kang, K.I.: Comparison of construction cost estimating models based on regression analysis, neural networks, and casebased reasoning. Build. Environ. 39(10), 1235–1242 (2004)CrossRefGoogle Scholar
  31. 31.
    Campania, R.: Prezzario dei lavori Pubblici. DEI Tipografia del Genio Civile, Roma (2015)Google Scholar
  32. 32.
    Mare, G., Manganelli, B., Nesticò, A.: The economic evaluation of investments in the energy sector: a model for the optimization of the scenario analyses. In: Murgante, B., Misra, S., Carlini, M., Torre, C.M., Nguyen, H.-Q., Taniar, D., Apduhan, B.O., Gervasi, O. (eds.) ICCSA 2013. LNCS, vol. 7972, pp. 359–374. Springer, Heidelberg (2013). doi: 10.1007/978-3-642-39643-4_27 CrossRefGoogle Scholar
  33. 33.
    Calavita, N., Calabrò, F., Della Spina, L.: Transfer of development rights as incentives for regeneration of illegal settlements. In: 1th International Symposium New Metropolitan Perspectives (ISTH 2020). Advanced Engineering Forum, vol. 11, pp. 639–646. Trans Tech Publications, Switzerland (2014). doi: 10.4028/www.scientific.net/AEF.11.639
  34. 34.
    Nesticò, A., Galante, M.: An estimate model for the equalisation of real estate tax: a case study. Int. J. Bus. Intell. Data Min. 10(1), 19–32 (2015). doi: 10.1504/IJBIDM.2015.069038. Inderscience Enterprises Ltd., Genève, SwitzerlandCrossRefGoogle Scholar
  35. 35.
    Aragona, S., Calabrò, F., Della Spina, L.: The evaluation culture to build a network of competitive cities in the mediterranean. In: 1th International Symposium New Metropolitan Perspectives (ISTH 2020). Advanced Engineering Forum, vol. 11, pp. 476–482. Trans Tech Publications, Switzerland (2014). doi: 10.4028/www.scientific.net/AEF.11.476
  36. 36.
    Greco, I., Bencardino, M.: The paradigm of the modern city: SMART and SENSEable Cities for smart, inclusive and sustainable growth. In: Murgante, B., Misra, S., Rocha, A.M.A.C., Torre, C., Rocha, J.G., Falcão, M.I., Taniar, D., Apduhan, B.O., Gervasi, O. (eds.) ICCSA 2014. LNCS, vol. 8580, pp. 579–597. Springer, Cham (2014). doi: 10.1007/978-3-319-09129-7_42 Google Scholar
  37. 37.
    Bencardino, M.: Demographic changes and urban sprawl in two middle-sized cities of campania region (Italy). In: Gervasi, O., Murgante, B., Misra, S., Gavrilova, M.L., Rocha, A.M.A.C., Torre, C., Taniar, D., Apduhan, Bernady O. (eds.) ICCSA 2015. LNCS, vol. 9158, pp. 3–18. Springer, Cham (2015). doi: 10.1007/978-3-319-21410-8_1 CrossRefGoogle Scholar
  38. 38.
    De Mare, G., Granata, M.F., Nesticò, A.: Weak and strong compensation for the prioritization of public investments: multidimensional analysis for pools. Sustainability 7(12), 16022–16038 (2015). doi: 10.3390/su71215798. MDPI AG, Basel, SwitzerlandCrossRefGoogle Scholar
  39. 39.
    Bencardino, M., Nesticò, A.: Demographic changes and real estate values. A quantitative model for analyzing the urban-rural linkages. Sustainability 9(4), 536 (2017). doi: 10.3390/su9040536 CrossRefGoogle Scholar
  40. 40.
    Guarini, M.R., Buccarini, C., Battisti, F.: Technical and Economic Evaluation of a Building Recovery by Public-Private Partnership in Rome (Italy). In: Stanghellini, S., Morano, P., Bottero, M., Oppio, A. (eds.) Appraisal: From Theory to Practice. GET, pp. 101–115. Springer, Cham (2017). doi: 10.1007/978-3-319-49676-4_8 CrossRefGoogle Scholar

Copyright information

© Springer International Publishing AG 2017

Authors and Affiliations

  • Antonio Nesticò
    • 1
    Email author
  • Gianluigi De Mare
    • 1
  • Biagino Frusciante
    • 1
  • Luigi Dolores
    • 1
  1. 1.Department of Civil EngineeringUniversity of SalernoFiscianoItaly

Personalised recommendations