Heuristic Algorithms for the Resource-Constrained Project Scheduling Problem: Classification and Computational Analysis

  • Chapter
Project Scheduling

Part of the book series: International Series in Operations Research & Management Science ((ISOR,volume 14))

Abstract

The resource-constrained project scheduling problem (RCPSP) can be given as follows. A single project consists of a set J = {0,1,…, n, n +1} of activities which have to be processed. Fictitious activities 0 and n + 1 correspond to the “project start” and to the “project end”, respectively. The activities are interrelated by two kinds of constraints. First, precedence constraints force activity j not to be started before all its immediate predecessor activities comprised in the set P j have been finished. Second, performing the activities requires resources with limited capacities. We have k resource types, given by the set K = {1,…,K}. While being processed, activity j requires r j,k units of resource type kK during every period of its non-preemptable duration p j . Resource type k has a limited capacity of R k at any point in time. The parameters pj,r j,k , and R k are assumed to be deterministic; for the project start and end activities we have pj = 0 and r j,k = 0 for all kK. The objective of the RCPSP is to find precedence and resource feasible completion times for all activities such that the makespan of the project is minimized. Figure 7:1 gives an example of a project comprising n = 6 activities which have to be scheduled subject to K = 1 renewable resource type with a capacity of 4 units. A feasible schedule with an optimal makespan of 13 periods is represented in Figure 7:2.

This is a preview of subscription content, log in via an institution to check access.

Access this chapter

Chapter
USD 29.95
Price excludes VAT (USA)
  • Available as PDF
  • Read on any device
  • Instant download
  • Own it forever
eBook
USD 169.00
Price excludes VAT (USA)
  • Available as PDF
  • Read on any device
  • Instant download
  • Own it forever
Softcover Book
USD 219.99
Price excludes VAT (USA)
  • Compact, lightweight edition
  • Dispatched in 3 to 5 business days
  • Free shipping worldwide - see info
Hardcover Book
USD 219.99
Price excludes VAT (USA)
  • Durable hardcover edition
  • Dispatched in 3 to 5 business days
  • Free shipping worldwide - see info

Tax calculation will be finalised at checkout

Purchases are for personal use only

Institutional subscriptions

Preview

Unable to display preview. Download preview PDF.

Unable to display preview. Download preview PDF.

References

  • Alvarez-Valdés, R. and J.M. Tamarit 1989a. Heuristic algorithms for resource-constrained project scheduling: A review and an empirical analysis. Advances in project scheduling. 113–134, Słowiński, R. and J. Węglarz (eds.). Elsevier, Amsterdam.

    Google Scholar 

  • Alvarez-Valdés, R., and J.M. Tamarit 1989b. Algoritmos heurísticos de-terministas y aleatorios en secuenciacón de proyectos con recursos limitados. Qüestiió 13, 173–191.

    Google Scholar 

  • Baar, T., Brucker, P., and S. Knust 1997. Tabu-search algorithms for the resource-constrained project scheduling problem. Technical Report, Univer-sität Osnabrück.

    Google Scholar 

  • Bean, J. 1994. Genetic algorithms and random keys for sequencing and optimization. ORSA Journal on Computing, 6, 2, 154–160.

    Article  Google Scholar 

  • Bell, C., and J. Han 1991. A new heuristic solution method in resource-constrained project scheduling. Naval Research Logistics 38, 315–331.

    Article  Google Scholar 

  • Bixby, N., and E. Boyed 1996. Using the CPLEX callable library. CPLEX Optimization Inc., Houston.

    Google Scholar 

  • Błażewicz, J., Lenstra, J., and A. Rinnooy Kan 1983. Scheduling subject to resource constraints: Classification and complexity. Discrete Applied Mathematics 5, 11–24.

    Article  Google Scholar 

  • Boctor, F. 1990. Some efficient multi-heuristic procedures for resource-constrained project scheduling. European Journal of Operational Research 49, 3–13.

    Article  Google Scholar 

  • Bouleimen, K., and H. Lecocq 1998. A new efficient simulated annealing algorithm for the resource-constrained project scheduling problem. Technical Report, Service de Robotique et Automatisation, Université de Liège.

    Google Scholar 

  • Brucker, P., and S. Knust 1998 Solving large-sized resource-constrained project scheduling problems. Handbook on recent advances in project scheduling. Chapter 18, J. Weglarz (ed.). Kluwer, Dordrecht.

    Google Scholar 

  • Brucker, P., Knust, S., Schoo, A., and O. Thiele 1998. A branch & bound algorithm for the resource-constrained project scheduling problem. European Journal of Operational Research, forthcoming.

    Google Scholar 

  • Cho, J.-H., and Y.-D. Kim 1997. A simulated annealing algorithm for resource constrained project scheduling problems. Journal of the Operational Research Society 48, 735–744.

    Google Scholar 

  • Christofides, N., Alvarez-Valdés, R., and J.M. Tamarit 1987. Project scheduling with resource constraints: A branch and bound approach. European Journal of Operational Research 29, 262–273.

    Article  Google Scholar 

  • Cooper, D. 1976. Heuristics for scheduling resource-constrained projects: An experimental investigation. Management Science 22, 11, 1186–1194.

    Article  Google Scholar 

  • Cooper, D. 1977. A note on serial and parallel heuristics for resource-constrained project scheduling. Foundations of Control Engineering 2, 4, 131–133.

    Google Scholar 

  • Davies, E. 1973. An experimental investigation of resource allocation in muli-tactivity projects. Operational Research Quarterly 24, 587–591.

    Article  Google Scholar 

  • Davis, E., and J. Patterson 1975. A comparison of heuristic and optimum solutions in resource-constrained project scheduling. Management Science 21, 944–955.

    Article  Google Scholar 

  • Della Croce, F. 1995. Generalized pairwise interchanges and machine scheduling. European Journal of Operational Research 83, 310–319.

    Article  Google Scholar 

  • Demeulemeester, E., and W. Herroelen 1997a. New benchmark results for the resource-constrained project scheduling problem. Management Science 43, 11, 1485–1492.

    Article  Google Scholar 

  • Dorndorf, U., and E. Pesch 1994. Evolution based learning in a job shop scheduling environment. Computers & Operations Research 22, 1, 25–40.

    Article  Google Scholar 

  • Drexl, A. 1991. Scheduling of project networks by job assignment. Management Science 37, 12, 1590–1602.

    Article  Google Scholar 

  • Elmaghraby, S. 1977. Activity networks: Project planning and control by network models. Wiley, New York.

    Google Scholar 

  • Elsayed, E. 1982. Algorithms for project scheduling with resource constraints. International Journal of Production Research 20, 1, 95–103.

    Article  Google Scholar 

  • Glover, F. 1989a. Tabu search — Part I. ORSA Journal on Computing 1, 190–206.

    Article  Google Scholar 

  • Glover, F. 1989b. Tabu search — Part II. ORSA Journal on Computing 2, 4–32.

    Article  Google Scholar 

  • Hartmann, S. 1998. A competitive genetic algorithm for resource-constrained project scheduling. Naval Research Logistics, forthcoming.

    Google Scholar 

  • +Hartmann, S., and R. Kolisch 1998. An experimental investigation of state-of-the-art heuristics for the resource-constrained project scheduling problem. Technical Report, Universität Kiel, 1998. In preparation.

    Google Scholar 

  • Herroelen, W., Demeulemeester, E., and B. De Reyck 1998}. A classification scheme for project scheduling}. Handbook on recent advances in project scheduling}. Chapter 1, J. Weglarz} (ed.). Kluwer, Dord

    Google Scholar 

  • Holland, H. 1975. Adaptation in natural and artificial systems. University of Michigan Press, Ann Arbor.

    Google Scholar 

  • Kelley, J. 1963. The critical-path method: Resources planning and scheduling. 347-365. Industrial scheduling, Muth, J. and G. Thompson (eds.). Prentice-Hall, New Jersey.

    Google Scholar 

  • Kim, Y.-D. 1995. A backward approach in list scheduling algorithms for multi-machine tardiness problems. Computers & Operations Research 22, 3, 307–319.

    Article  Google Scholar 

  • Klrkpatrick, S., Gelatt Jr., C. D., And M.P. Vecchi 1983. Optimization by simulated annealing. Science 220, 671–680.

    Article  Google Scholar 

  • Kohlmorgen, U., Schmeck, H., And K. Haase 1998. Experiences with fine-grained parallel genetic algorithms. Annals of Operations Research, forthcoming.

    Google Scholar 

  • Kolisch, R. 1995. Project scheduling under resource constraints — Efficient heuristics for several problem classes. Physica, Heidelberg.

    Google Scholar 

  • Kolisch, R. 1996a. Serial and parallel resource-constrained project scheduling methods revisited: Theory and computation. European Journal of Operational Research 90, 320–333.

    Article  Google Scholar 

  • Kolisch, R. 1996b. Efficient priority rules for the resource-constrained project scheduling problem. Journal of Operations Management 14, 3, 179–192.

    Article  Google Scholar 

  • Kolisch, R., and A. Drexl 1996. Adaptive search for solving hard project scheduling problems. Naval Research Logistics 43, 23–40.

    Article  Google Scholar 

  • Kolisch, R., and R. Padman 1997. An integrated survey of project scheduling. Technical Report 463, Manuskripte aus den Instituten für Betriebswirt-schaftslehre der Universität Kiel.

    Google Scholar 

  • Kolisch, R., Schwindt, C., and A. Sprecher 1998. Benchmark instances for project scheduling problems. Handbook on recent advances in project scheduling. Chapter 9, J. Weglarz (ed.). Kluwer, Dordrecht.

    Google Scholar 

  • Kolisch, R., and A. Sprecher 1996. PSPLIB — a project scheduling problem library. European Journal of Operational Research 96, 205–216.

    Article  Google Scholar 

  • Kolisch, R., Sprecher, A., and A. Drexl 1995. Characterization and generation of a general class of resource-constrained project scheduling problems. Management Science 41, 10, 1693–1703.

    Article  Google Scholar 

  • Lawrence, S. 1985. Resource constrained project scheduling — A computational comparison of heuristic scheduling techniques. Technical Report, Graduate School of Industrial Administration, Carnegie-Mellon University, Pittsburgh.

    Google Scholar 

  • Lee, J.-K., and Y.-D. Kim 1996. Search heuristics for resource constrained project scheduling. Journal of the Operational Research Society 47, 678–689.

    Google Scholar 

  • Leon, V., and B. Ramamoorthy 1995. Strength and adaptability of problem-space based neighborhoods for resource-constrained scheduling. OR Spektrum 17, 2/3, 173–182.

    Google Scholar 

  • Li, R.-Y., and J. Willis 1992. An iterative scheduling technique for resource-constrained project scheduling. European Journal of Operational Research 56, 370–379.

    Article  Google Scholar 

  • Mausser, H., and S. Lawrence 1998. Exploiting block structure to improve resource-constrained project schedules. Metaheuristics, forthcoming.

    Google Scholar 

  • Mlngozzi, A., Maniezzo, V., Rlcciardelli, S., And L. Bianco 1998. An exact algorithm for project scheduling with resource constraints based on a new mathematical formulation. Management Science, forthcoming.

    Google Scholar 

  • Naphade, K., Wu, S., and R. Storer 1997. Problem space search algorithms for resource-constrained project scheduling. Annals of Operations Research 70, 307–326.

    Article  Google Scholar 

  • Oguz, O., and H. Bala 1994. A comparative study of computational procedures for the resource constrained project scheduling problem. European Journal of Operational Research 72, 406–416.

    Article  Google Scholar 

  • Özdamar, L., and G. Ulusoy 1994. A local constraint based analysis approach to project scheduling under general resource constraints. European Journal of Operational Research 79, 287–298.

    Article  Google Scholar 

  • Özdamar, L., and G. Ulusoy 1996a. A note on an iterative forward/backward scheduling technique with reference to a procedure by Li and Willis. European Journal of Operational Research 89, 400–407.

    Article  Google Scholar 

  • Özdamar, L., and G. Ulusoy 1996b. An iterative local constraint based analysis for solving the resource constrained project scheduling problem. Journal of Operations Management 14, 3, 193–208.

    Article  Google Scholar 

  • Patterson, J. 1973. Alternate methods of project scheduing with limited resources. Naval Research Logistics Quarterly 23, 767–784.

    Article  Google Scholar 

  • Patterson, J. 1976. Project scheduling: The effects of problem structure on heuristic performance. Naval Research Logistics Quarterly 20, 95–123.

    Article  Google Scholar 

  • Pinson, E., Prins, C., and F. Rullier 1994. Using tabu search for solving the resource-constrained project scheduling problem. Proceedings of the 4. International Workshop on Project Management and Scheduling, 102–106, Leuven.

    Google Scholar 

  • Pollack-Johnson, B. 1995. Hybrid structures and improving forecasting and scheduling in project management. Journal of Operations Management 12, 101–117.

    Article  Google Scholar 

  • Pritsker, A., Watters, L., and P. Wolfe 1969. Multiproject scheduling with limited resources: A zero-one programming approach. Management Science 16, 93–107.

    Article  Google Scholar 

  • Sampson, S., and E. Weiss 1993. Local search techniques for the generalized resource constrained project scheduling problem. Naval Research Logistics 40, 665–675.

    Article  Google Scholar 

  • Schirmer, A., and S. Riesenberg 1997. Parameterized heuristics for project scheduling — Biased random sampling methods. Technical Report 456, Manu-skripte aus den Instituten für Betriebswirtschaftslehre der Universität Kiel.

    Google Scholar 

  • Schirmer, A. 1998. Case-based reasoning and improved adaptive search for project scheduling. Technical Report 472, Manuskripte aus den Instituten für Betriebswirtschaftslehre der Universität Kiel.

    Google Scholar 

  • Schutten, J. 1996. List scheduling revisited. Operations Research Letters 18, 167–170.

    Article  Google Scholar 

  • Shaffer, L., Ritter, J., and W. Meyer 1965. The critical-path method. McGraw Hill, New York.

    Google Scholar 

  • Sprecher, A. 1996. Solving the RCPSP efficiently at modest memory requirements. Technical Report 425, Manuskripte aus den Instituten für Betriebswirtschaftslehre der Universität Kiel.

    Google Scholar 

  • Sprecher, A., Kolisch, R., and A. Drexl 1995. Semi-active, active, and non-delay schedules for the resource-constrained project scheduling problem. European Journal of Operational Research 80, 94–102.

    Article  Google Scholar 

  • Stinson, J., Davis, E., and B. Khumawala 1978. Multiple resource-constrained scheduling using branch and bound. AIIE Transactions 10, 252–259.

    Article  Google Scholar 

  • Storer, R., Wu, S., and R. Vaccari 1992. New search spaces for sequencing problems with application to job shop scheduling. Management Science 38, 10, 1495–1509.

    Article  Google Scholar 

  • Thesen, A. 1976. Heuristic scheduling of activities under resource and precedence restrictions. Management Science 23, 4, 412–422.

    Article  Google Scholar 

  • Thomas, P., and S. Salhi 1997. An investigation into the relationship of heuristic performance with network-resource characteristics. Journal of the Operational Research Society 48, 1, 34–43.

    Google Scholar 

  • Ulusoy, G., and L. Özdamar 1989. Heuristic performance and network/resource characteristics in resource-constrained project scheduling. Journal of the Operational Research Society 40, 12, 1145–1152.

    Google Scholar 

  • Ulusoy, G., and Özdamar, L. 1994. A constraint-based perspective in resource constrained project scheduling. International Journal of Production Research 32, 3, 693–705.

    Article  Google Scholar 

  • Valls, V., Pérez, M., and M. Quintanilla 1992. Heuristic performance in large resource-constrained projects. Technical Report 92-2, Departament D’Estadistica I Invecigacio Operativa, Universitat de Valencia.

    Google Scholar 

  • Whitehouse, G., and J. Brown 1979. Genres: An extension of Brooks algorithm for project scheduling with resource constraints. Computers & Industrial Engineering 3, 261–268.

    Article  Google Scholar 

Download references

Author information

Authors and Affiliations

Authors

Editor information

Editors and Affiliations

Rights and permissions

Reprints and permissions

Copyright information

© 1999 Springer Science+Business Media New York

About this chapter

Cite this chapter

Kolisch, R., Hartmann, S. (1999). Heuristic Algorithms for the Resource-Constrained Project Scheduling Problem: Classification and Computational Analysis. In: Węglarz, J. (eds) Project Scheduling. International Series in Operations Research & Management Science, vol 14. Springer, Boston, MA. https://doi.org/10.1007/978-1-4615-5533-9_7

Download citation

  • DOI: https://doi.org/10.1007/978-1-4615-5533-9_7

  • Publisher Name: Springer, Boston, MA

  • Print ISBN: 978-1-4613-7529-6

  • Online ISBN: 978-1-4615-5533-9

  • eBook Packages: Springer Book Archive

Publish with us

Policies and ethics