Propagation of Cumulative Constraints

  • Chapter
  • 977 Accesses

Part of the book series: International Series in Operations Research & Management Science ((ISOR,volume 39))

Abstract

Cumulative resource constraints represent the fact that activities A i use some amount cap(A i ) of resource throughout their execution. For a fully elastic activity A i , the cap(A i ) variable is not meaningful and we use a variable E(A i ) that represents the global “energy” required by the activity on the resource. Of course, for a non-elastic activity, we have E(A i ) = cap(A i )proc(A i ). In all case, enough resource must be allocated to activities, i.e., E(A i ) = Σ t E(A i , t), where E(A i , t) is the amount of resource used at t by A i . Recall that if A i is not an elastic activity, there are some strong relations between E(A i , t) and X(A i , t): E(A i , t) = X(A i , t)cap(A i ) For elastic activities, we have a weaker relation between the variables: [E(A i , t) # 0] ⇔ [X(A i i,t) # 0]. Generally speaking, the cumulative resource constraint can be stated as follows:

$$ \forall t\sum\limits_i {E(A_i ,t)} \le cap $$

In the non-preemptive case, it can be rewritten as,

$$ \forall t\sum\limits_{start(A_i ) \le t < end(A_i )} {cap(A_i )} \le cap $$

and in the preemptive case as,

$$ \forall t\sum\limits_{start(A_i ) \le t < end(A_i )} {X(A_i ,t)cap(A_i )} \le cap $$

In the following, we note c i and e i the minimal amount of the capacity (resp. of the energy) of the resource required by A i . Finally we note C the maximum value in the domain of the resource capacity. In this chapter, we recall the most well-known techniques used to propagate the cumulative resource constraint. We focus on the fully elastic case in Section 3.1, on the preemptive case in Section 3.2 and, finally, on the non-preemptive case in Section 3.3.

This is a preview of subscription content, log in via an institution.

Buying options

Chapter
USD   29.95
Price excludes VAT (USA)
  • Available as PDF
  • Read on any device
  • Instant download
  • Own it forever
eBook
USD   169.00
Price excludes VAT (USA)
  • Available as PDF
  • Read on any device
  • Instant download
  • Own it forever
Softcover Book
USD   219.99
Price excludes VAT (USA)
  • Compact, lightweight edition
  • Dispatched in 3 to 5 business days
  • Free shipping worldwide - see info
Hardcover Book
USD   219.99
Price excludes VAT (USA)
  • Durable hardcover edition
  • Dispatched in 3 to 5 business days
  • Free shipping worldwide - see info

Tax calculation will be finalised at checkout

Purchases are for personal use only

Learn about institutional subscriptions

Preview

Unable to display preview. Download preview PDF.

Unable to display preview. Download preview PDF.

Author information

Authors and Affiliations

Authors

Rights and permissions

Reprints and permissions

Copyright information

© 2001 Springer Science+Business Media New York

About this chapter

Cite this chapter

Baptiste, P., Le Pape, C., Nuijten, W. (2001). Propagation of Cumulative Constraints. In: Constraint-Based Scheduling. International Series in Operations Research & Management Science, vol 39. Springer, Boston, MA. https://doi.org/10.1007/978-1-4615-1479-4_3

Download citation

  • DOI: https://doi.org/10.1007/978-1-4615-1479-4_3

  • Publisher Name: Springer, Boston, MA

  • Print ISBN: 978-1-4613-5574-8

  • Online ISBN: 978-1-4615-1479-4

  • eBook Packages: Springer Book Archive

Publish with us

Policies and ethics