Just-in-Time Management of a Building Project in the Middle-East

  • Low Sui PhengEmail author
  • Thilini Shiromani Jayawickrama
Chapter
Part of the Springer Optimization and Its Applications book series (SOIA, volume 60)

Abstract

The Just-in-Time (JIT) philosophy originated from and is widely used in, but not limited to the manufacturing industry. Many studies have been conducted to examine the possibility of adopting JIT principles to specific areas of the construction industry. This study aims to identify the application of the JIT principles for a building project in a region of the Middle-East from the perspective of the main contractor through a case study approach. The study provides anecdotal evidence of the project applying the seven principles of JIT successfully to improve productivity and quality standards, which helped the main contractor to achieve the target completion date. The study also reveals top management commitment as a major underpinning for implementing the JIT system as well as some of the hindrances which may be inevitable because of the corresponding barriers encountered. Some of these barriers are due to the inherent features of the construction industry such as the multidisciplinary nature of practices and complexity of projects. Other barriers are region-specific and include perceptibly lenient and less effective resource management techniques and philosophies of many local clients driven by their high liquidity and strong spending capacities.

Keywords

Construction Industry Construction Project Employee Involvement Autoclave Aerate Concrete Pull System 
These keywords were added by machine and not by the authors. This process is experimental and the keywords may be updated as the learning algorithm improves.

Notes

Acknowledgment

The authors are grateful to the management and staff involved with the case study project for offering the second author the opportunity to observe how best practices in construction project management may be facilitated through the JIT philosophy. It is hoped that the best practices presented can further demonstrate and showcase the applicability of JIT principles in the construction setting.

References

  1. 1.
    Liker, J.K,: The Toyota Way. McGraw-Hill, New York, United States (2004)Google Scholar
  2. 2.
    Low, S.P.: The just-in-time concept to improving manufacturing productivity: is it applicable to the construction industry? Construction Paper Series 8, Chartered Institute of Building, 1-8 (1992)Google Scholar
  3. 3.
    Low, S.P., Ang, G.K.: Integrating JIT and 5-S concepts for construction site management: a case study. International Journal of Construction Management 3(1), 31-47 (2003)Google Scholar
  4. 4.
    Low, S.P., Choong, J.C. : Just-in-time management of precast concrete components. Journal of Construction Engineering and Management 127(6), 494-501 (2001)CrossRefGoogle Scholar
  5. 5.
    Low, S.P. and Mok, S.H.: The application of JIT philosophy to construction: a case study in site layout. Construction Management and Economics 17(5), 657-668 (1999)CrossRefGoogle Scholar
  6. 6.
    Wantuck, K.A.: Just-In-Time for America: A common sense production strategy. The Forum Ltd, Milwaukee, United States (1989)Google Scholar
  7. 7.
    Wu, M., Low, S.P., Xu, M.Z., Shen, Q.P.: The EOQ-JIT Cost Indifference Point Theory and Its Applications in the Ready-mixed Concrete Industry. Hong Kong Polytechnic University Press, Hong Kong SAR, China. (2010)Google Scholar

Copyright information

© Springer Science+Business Media, LLC 2012

Authors and Affiliations

  • Low Sui Pheng
    • 1
    Email author
  • Thilini Shiromani Jayawickrama
    • 1
  1. 1.Department of BuildingNational University of SingaporeSingaporeSingapore

Personalised recommendations