Outcomes of Current Project Management Practices in South Africa

  • Godfrey MonyaneEmail author
  • Fidelis Emuze
  • Bankole Awuzie
  • Gerrit Crafford
Conference paper
  • 71 Downloads
Part of the Lecture Notes in Mechanical Engineering book series (LNME)

Abstract

With the decline of the current economic conditions in South Africa, project performance is a great concern that needs attention. A qualitative multiple case study strategy and semi-structured interviews were undertaken to determine the outcomes of current project management practices in South Africa. In terms of the performance of projects, the status quo paints a disconsolate picture. The poor performance continues to dominate the construction sector, especially in the public sector. Findings reveal protracted processes, and the use of unqualified and inexperienced contractors contribute to the poor performance of public sector projects. In addition, ineffective initiatives to curb the abuse of the procurement processes are directly affecting the outcomes of construction projects due to loopholes in the procurement process, and if this status quo remains, the sector will continue to have a bad image and continued waste of taxpayers’ money will not cease until the public sector remove non-value adding activities in their operations.

Keywords

Cost performance Project performance Project management Public sector projects Time performance 

References

  1. Ahiaga-Dagbui DD, Smith SD, Love PE, Ackermann F (2015) Spotlight on construction cost overrun research: superficial, replicative and stagnatedGoogle Scholar
  2. Aiyetan A, Smallwood J, Shakantu W (2011) A systems thinking the approach to eliminate delays on building construction projects in South Africa. Acta Structilia 18:19–39Google Scholar
  3. Ali A-S, Kamaruzzaman S-N, Sulaiman R, Cheong Peng Y (2010) Factors affecting housing maintenance cost in Malaysia. J Facili Manage 8:285–298CrossRefGoogle Scholar
  4. Auma E (2014) Factors affecting the performance of construction projects in Kenya: a survey of low-rise buildings in Nairobi Central Business District. Int J Bus Manage 2:115Google Scholar
  5. Bello W (2018) Project performance diagnostics: a model for assessing construction project performance in Nigeria. University of Salford, ManchesterGoogle Scholar
  6. Fellows R, Liu A (2015) Research methods for construction. WileyGoogle Scholar
  7. Flyvbjerg B (2011) Over budget, over time, over and over again: managing major projectsGoogle Scholar
  8. Flyvbjerg B, Garbuio M, Lovallo D (2009) Delusion and deception in large infrastructure projects: two models for explaining and preventing executive disaster. Calif Manage Rev 51:170–194CrossRefGoogle Scholar
  9. Gbahabo PT, Ajuwon OS (2017) Effects of project cost overruns and schedule delays in Sub-Saharan Africa. Eur J Interdisc Stud 3:46–59CrossRefGoogle Scholar
  10. Kadiri D, Shittu AA (2015) Causes of time overrun in building projects in Nigeria: contracting and consulting perspectives. Int J Civil Eng Constr Estate Manage 3:50–56Google Scholar
  11. Kikwasi G (2012) Causes and effects of delays and disruptions in construction projects in Tanzania. Australas J Constr Econ Build-Conf Ser 52–59Google Scholar
  12. Kulatunga U, Amaratunga D, Haigh R (2007) Performance measurement in the construction research and development. Int J Prod Perform Manage 56:673–688CrossRefGoogle Scholar
  13. Lavagnon I (2012) Project management for development in Africa: why projects are failing and what can be done about it. Proj Manage J 43:27–41CrossRefGoogle Scholar
  14. Leedy P, Ormrod J (2010) Practical research planning and design, 9th edn. Pearson Education International, BostonGoogle Scholar
  15. Love P (2011) Plugging the gaps’ between optimum bias and strategic misrepresentation and infrastructure cost overruns. Procedia Eng 14:1197–1204CrossRefGoogle Scholar
  16. Love PE, Sing C-P (2013) Determining the probability distribution of rework costs in construction and engineering projects. Struct Infrastruct Eng 9:1136–1148CrossRefGoogle Scholar
  17. Merrow EW (2011) Industrial megaprojects: concepts, strategies, and practices for success. WileyGoogle Scholar
  18. Niven PR (2002) Balanced scorecard step-by-step: maximizing performance and maintaining results. WileyGoogle Scholar
  19. Odediran SJ, Windapo AO (2014) A systematic review of factors influencing the cost performance of building projects. Postgrad Conf 2014:501Google Scholar
  20. Yin RK (2014) Case study research: design and methods, 5th edn. Thousand OaksGoogle Scholar
  21. Zawawi WA, Amila N, Azman N, Izyan NF, Kamar S, Shamil M (2010) Sustainable construction practice: a review of change orders (CO) in construction projectsGoogle Scholar
  22. Zou PX, Zhang G, Wang J (2007) Understanding the key risks in construction projects in China. Int J Project Manage 25:601–614CrossRefGoogle Scholar

Copyright information

© Springer Nature Singapore Pte Ltd. 2020

Authors and Affiliations

  • Godfrey Monyane
    • 1
    Email author
  • Fidelis Emuze
    • 1
  • Bankole Awuzie
    • 1
  • Gerrit Crafford
    • 2
  1. 1.Department of Built EnvironmentCentral University of Technology FSBloemfonteinSouth Africa
  2. 2.Department of Quntity SurveyingNelson Mandela UniversityPort ElizabethSouth Africa

Personalised recommendations