Study on Maintenance Dredging for Navigable Depth Assurance in the Macro-tidal Hooghly Estuary

  • V. Maheshvaran
  • K. MuraliEmail author
  • V. Sundar
  • K. Chitra
Conference paper
Part of the Lecture Notes in Civil Engineering book series (LNCE, volume 23)

Abstract

Hooghly Estuary is a tide-dominated estuary in the east coast of India, experiencing heavy siltation in the navigation channel. This frequent siltation affects the movement of vessels, thus, hampering the efficiency of the port. The quantity of siltation is related to the physical and environmental conditions and the geometric configuration of the entrance as well as the navigation channels. This study aims at investigating the possibility of smooth navigable channel to the Haldia Dock Complex with a minimum quantity of maintenance dredging. The monitoring of the channel through bathymetry survey at regular intervals has been carried out. The filed survey involved identification of the zones of siltation, changes in the depth and estimation of sediment volumes at 10 different sections along the Eden bar. It was found in the study that the siltation depth varies between the spring and neap tide periods due to the variation in the tidal currents. From the field monitoring surveys, it is found that there is predominant erosion from neap-to-spring tidal cycle. These aspects are brought out in the manuscript along with the stability details of the Eden channel, throughout the year.

Keywords

Dredging Estuary Navigation channel Siltation Tide-dominated estuary 

Notes

Acknowledgements

The authors wish to record their sincere thanks to the Authorities of Kolkata Port Trust for their valuable support during the survey and technical discussion.

References

  1. 1.
    Dalrymple RW, Zaitlin BA, Boyd R (1992) Estuarine facies models: conceptual basis and stratigraphic implications: perspective. J Sediment Res 62(6):1130–1146CrossRefGoogle Scholar
  2. 2.
    Nandy Sreetapa, Bandyopadhyay Sunando (2011) Trend of sea level change in the Hugli Estuary India. Indian J Marine Sci 40(6):802–812Google Scholar
  3. 3.
    Dubey Rajesh P, Samarawickrama S, Gunaratna PP, Halgahawatta L, Pathirana KPP, Raveenthiran K, Subasingha K, Das B, Sugandika TAN (2013) Mathematical model studies for River regulatory measures for the improvement of draft in Hoogly Estuary, India. Evol Trends Eng Technol 2(84):1–12Google Scholar
  4. 4.
    Sanyal T, Chatterjee AK, Mandal GC (2000) Erosion—Deposition in Hooghly Estuary. Def Sci J 50(3):335–339CrossRefGoogle Scholar
  5. 5.
    Bhaskaran PK, Mangalagiri S, Bonthu S (2014) Dredging maintenance plan for the Kolkata port India. Curr Sci 107(7):1125–1136Google Scholar
  6. 6.
    Rehitha TV, Ullas N, Vineetha G, Benny PY, Madhu NV, Revichandran C (2017) Impact of maintenance dredging on macrobenthic community structure of a tropical estuary. Ocean Coast Manag 144:71–82CrossRefGoogle Scholar

Copyright information

© Springer Nature Singapore Pte Ltd. 2019

Authors and Affiliations

  • V. Maheshvaran
    • 1
  • K. Murali
    • 1
    Email author
  • V. Sundar
    • 1
  • K. Chitra
    • 2
  1. 1.Department of Ocean EngineeringIndian Institute of Technology MadrasChennaiIndia
  2. 2.Samudra Consultants Pvt Ltd, IITM Incubation CellChennaiIndia

Personalised recommendations