Change Order Impact on Construction Industry of Pakistan

  • Muhammad AltafEmail author
  • Muhammad Ali Musarat
  • Azizullah Khan
  • Zohaib Shoukat
  • Usman Salahuddin
Conference paper
Part of the Lecture Notes in Civil Engineering book series (LNCE, volume 53)

Abstract

Change order is the alteration in the contract documents which signed before a project between two parties. The impact of change order fluctuates the budget as well as the duration of the project. Change order has been called the biggest cause of dispute between the contractor and client. The aim of this research was to find out the factors that cause change order and articulate a guideline to overcome the problems for stakeholders of construction industry. From the perspective of expertise, stakeholders of construction industry and literature review a questionnaire was designed and conducted an exploratory survey. The data collected from 102 respondents were analyzed through Statistical Packages of Social Sciences (SPSS-23) and MS Excel for reliability check. 32 influential factors identified through an exploratory survey from the stakeholders of construction industry. Five factors like scope of the project, defects in drawings, client financial problems and lack of skilled labor and role of technology concluded high-rank factors by Relative importance index (RII). To avoid the adverse effects of these factors and disputes between the different parties, the project scope must be identified from the beginning of the project. The drawings should be cleared to the owner and project should be managed properly. Majority of the projects are affected by the change order, it is therefore suggested to focus on the critical factors to avoid the effects.

Keywords

Change order Construction industry Relative importance index Critical factors Khyber pakhtunkhwa Pakistan 

References

  1. 1.
    Ade-Ojo CO, Babalola AA (2013) Cost and time performance of construction projects under due process reform in Nigeria. Int J Eng Sci 3(6):1–6Google Scholar
  2. 2.
    Alaryan A (2014) Causes and effects of change orders on construction projects in Kuwait. Int J Eng Res Appl 4(7):01–08Google Scholar
  3. 3.
    Hanna AS, Camlic R, Peterson PA, Nordheim EV (2002) Quantitative definition of projects impacted by change orders. J Constr Eng Manag 128(1):57–64CrossRefGoogle Scholar
  4. 4.
    Ibbs CW, Wong CK, Kwak YH (2001) Project change management system. J Manag Eng 17(3):159–165CrossRefGoogle Scholar
  5. 5.
    Ismail A, Pourrostam T, Soleymanzadeh A, Ghouyounchizad M (2012) Factors causing variation orders and their effects in roadway construction projects. Res J Appl Sci Eng Technol 4(23):4969–4972Google Scholar
  6. 6.
    Iyagba RO, Ijaola IA (2012) A comparative study of causes of change orders in public construction project in Nigeria and Oman. J Emerg Trends Econ Manag Sci 3(5):495–501Google Scholar
  7. 7.
    James MB (2017) Effective change order management. Long International, Inc.Google Scholar
  8. 8.
    Keane P, Sertyesilisik B, Ross AD (2010) Variations and change orders on construction projects. J Legal Aff Dispute Resolut Eng Constr 2(2):89–96CrossRefGoogle Scholar
  9. 9.
    Kegan R, Lahey LL (2001) The real reason people won’t change. HBR’s 10 Must Reads on Change, p 77Google Scholar
  10. 10.
    Lokhande MA, Ahmed FSY (2015) Assessing consequences of change request impact in construction industry of YEMEN: an explorative Likert-Scale based survey design. Management 5(5):141–147Google Scholar
  11. 11.
    Osman Z, Omran A, Foo CK (2009) The potential effects of variation orders in construction projects. J Eng 2:141–152Google Scholar
  12. 12.
    Olsen D, Killingsworth R, Page B (2012) Change order causation; who is the guilty party. In: 48th ASC annual international conference proceedings, pp 1–9Google Scholar
  13. 13.
    Pourrostam T, Ismail A (2011) Significant factors causing and effects of delay in Iranian construction projects. Aust J Basic Appl Sci 5(7):450–456Google Scholar
  14. 14.
    Stasis A, Whyte J, Dentten R (2013) A critical examination of change control processes. Procedia CIRP 11:177–182CrossRefGoogle Scholar
  15. 15.
    Staiti M, Othman M, Jaaron AA (2016) Impact of change orders in construction sector in the west bank. In: International conference on industrial engineering and operations managementGoogle Scholar
  16. 16.
    Sun M, Meng X (2009) Taxonomy for change causes and effects in construction projects. Int J Project Manage 27(6):560–572CrossRefGoogle Scholar
  17. 17.
    Yana AGA, Rusdhi HA, Wibowo MA (2015) Analysis of factors affecting design changes in construction project with partial least square (PLS). Procedia Eng 125:40–45CrossRefGoogle Scholar

Copyright information

© Springer Nature Switzerland AG 2020

Authors and Affiliations

  • Muhammad Altaf
    • 1
    Email author
  • Muhammad Ali Musarat
    • 1
  • Azizullah Khan
    • 1
  • Zohaib Shoukat
    • 1
  • Usman Salahuddin
    • 1
  1. 1.Department of Civil EngineeringSarhad University of Science and Information TechnologyPeshawarPakistan

Personalised recommendations