Designing a Procurement Management Model to Reduce Project Delays in a Hydraulic and Automation Systems Company

  • Melanie VereauEmail author
  • Jose RojasEmail author
  • Daniel AderholdEmail author
  • Carlos RaymundoEmail author
  • Francisco DominguezEmail author
Conference paper
Part of the Advances in Intelligent Systems and Computing book series (AISC, volume 1026)

Abstract

This study focuses on the factors that cause project delays in an industrial hydraulic company. More specifically, the article also addresses the development of on-demand engineered products and the impact of the procurement process on delays. As part of the investigation, the authors assessed the historical data of the projects completed in 2017 before determining the critical path for each project in an attempt to identify which project stages may be improved. After further assessing the resulting data, the planning and procurement procedures were deemed as requiring improvement. Next, the article proposes a training plan and new procedures based on the Project Management Body of Knowledge guidelines for Engineer-to-Order projects. In conclusion, the results showed that delays were effectively reduced after implementing these new procedures in both Project Management stages.

Keywords

Delays Project Management PMBOK ETO Hydraulics 

References

  1. 1.
    Mello, M.H., Strandhagen, J.O., Alfnes, E.: The role of coordination in avoiding project delays in an engineer-to-order supply chain. J. Manuf. Technol. Manag. 26(3), 429–454 (2015).  https://doi.org/10.1108/JMTM-03-2013-0021CrossRefGoogle Scholar
  2. 2.
    Ghiasi, V., Kaivan, E., Arzjani, N., Arzjani, D.: Analyzing the causes of delay in development projects by fuzzy analysis. Int. J. Qual. Reliab. Manag. 34, 1412–1430 (2017).  https://doi.org/10.1108/IJQRM-08-2016-0134CrossRefGoogle Scholar
  3. 3.
    Pham, L.H., Hadikusumo, H.: Schedule delays in engineering, procurement, and construction petrochemical projects in Vietnam. Int. J. Energy Sect. Manage. 8(1), 3–26 (2014)CrossRefGoogle Scholar
  4. 4.
    Mello, M.H., Strandhagen, J.O., Alfnes, E.: Analyzing the factors affecting coordination in engineer-to-order supply chain. Int. J. Oper. Prod. Manag. 35(7), 1005–1031 (2015)CrossRefGoogle Scholar
  5. 5.
    Zare, R., Chavez, P., Raymundo, C., Rojas, J.: Collaborative culture management model to improve the performance in the inventory management of a supply chain. In: 2018 Congreso Internacional de Innovacion y Tendencias en Ingenieria, CONIITI 2018 - Proceedings (2018). 8587073Google Scholar

Copyright information

© Springer Nature Switzerland AG 2020

Authors and Affiliations

  1. 1.Ingeniería de Gestión EmpresarialUniversidad Peruana de Ciencias Aplicadas (UPC)LimaPeru
  2. 2.Dirección de InvestigaciónUniversidad Peruana de Ciencias Aplicadas (UPC)LimaPeru
  3. 3.Escuela Superior de Ingeniería InformáticaUniversidad Rey Juan CarlosMadridSpain

Personalised recommendations