Investigation of the Earned Value Method (EVM) Applicability for Construction Operations Affected by the Learning Phenomenon

  • Conference paper
  • First Online:
The 10th International Conference on Engineering, Project, and Production Management

Abstract

The Earned Value Method (EVM) has been extensively applied for the analysis of construction projects. However, in cases where the productivity is not constant, but rather varies due to accelerations attributed to the learning phenomenon, it is challenging to assess the implications on productivity estimation and forecasting. In that sense, such an investigation is crucial for the scheduling and coordination of the remaining works in a realistic manner. The purpose of this paper is to compare the progress reporting results using the Earned Value method both for the theoretical project time schedule (without learning) and the actual on-site scheduling following the learning curve. A real, large-scale infrastructure project is used as a case study. The research method involved the “transformation” of productivity data to cost data, with the purpose of quantifying the productivity improvements through the use of statistical learning models. The straight-line model was used, due to its wide acceptance in related studies. An algorithmic approach is developed and assessed via, inter alia, the Schedule Variance (SV) and the Cost Variance (CV) indices. The results of the research indicate that EVM is significantly affected by the learning phenomenon, which, if neglected, leads to ineffective decision making procedures, regarding the deployment of project resources.

This is a preview of subscription content, log in via an institution to check access.

Access this chapter

Chapter
USD 29.95
Price excludes VAT (USA)
  • Available as PDF
  • Read on any device
  • Instant download
  • Own it forever
eBook
USD 129.00
Price excludes VAT (USA)
  • Available as EPUB and PDF
  • Read on any device
  • Instant download
  • Own it forever
Softcover Book
USD 169.99
Price excludes VAT (USA)
  • Compact, lightweight edition
  • Dispatched in 3 to 5 business days
  • Free shipping worldwide - see info
Hardcover Book
USD 169.99
Price excludes VAT (USA)
  • Durable hardcover edition
  • Dispatched in 3 to 5 business days
  • Free shipping worldwide - see info

Tax calculation will be finalised at checkout

Purchases are for personal use only

Institutional subscriptions

References

  • Afshari H, Jaber MY, Searcy C (2019) Investigating the effects of learning and forgetting on the feasibility of adopting additive manufacturing in supply chains. Comput Ind Eng 128:576–590

    Article  Google Scholar 

  • Anbari FT (2003) Earned value project management method and extension. Project Manag J 34(4):12–23

    Article  Google Scholar 

  • Czarnigowska A (2008) Earned value method as a tool for project control. Budownictwo i Architektura 3:15–32

    Google Scholar 

  • Everett JG, Farghal S (1994) Learning curve predictors for construction field operations. J Constr Eng Manag 120(3):603–616

    Article  Google Scholar 

  • Lee B, Lee H, Park M, Kim H (2015) Influence factors of learning-curve effect in high-rise building constructions. J Constr Eng Manag 141(8):04015019

    Article  Google Scholar 

  • Olawale Y, Sun M (2015) Construction project control in the UK: current practice, existing problems and recommendations for future improvement. Int J Project Manage 33(3):623–637

    Article  Google Scholar 

  • Panas A, Pantouvakis JP (2010) Evaluating research methodology in construction productivity studies. Built Human Environ Rev 3(1):63–85

    Google Scholar 

  • Panas A, Pantouvakis JP (2014) Simulation-based and statistical analysis of the learning effect in floating caisson construction operations. J Constr Eng Manag 140(1):04013033

    Article  Google Scholar 

  • Panas A, Pantouvakis JP (2018) On the use of learning curves for the estimation of construction productivity. Int J Constr Manag. https://doi.org/10.1080/15623599.2017.1326302

    Article  Google Scholar 

  • Pantouvakis JP, Panas A (2013) Computer simulation and analysis framework for floating caisson construction operations. Autom Constr 36:196–207

    Article  Google Scholar 

  • Pellegrino R, Costantino N (2018) An empirical investigation of the learning effect in concrete operations. Eng, Constr Archit Manag 25(3):342–357

    Article  Google Scholar 

  • Plaza M, Turetken O (2009) A model-based DSS for integrating the impact of learning in project control. Decis Support Syst 47(4):488–499

    Article  Google Scholar 

  • Thomas HR (2009) Construction learning curves. Pract Period Struct Des Constr 14(1):14–20

    Article  Google Scholar 

  • Thomas HR, Mathews CT, Ward JG (1986) Learning curve models of construction productivity. J Constr Eng Manag 112(2):245–259

    Article  Google Scholar 

  • Zayed T, Sharifi MR, Baciu S, Amer M (2008) Slip-form application to concrete structures. J Constr Eng Manag 134:157–168

    Article  Google Scholar 

Download references

Author information

Authors and Affiliations

Authors

Corresponding author

Correspondence to Dimitrios Karagiannakidis .

Editor information

Editors and Affiliations

Rights and permissions

Reprints and permissions

Copyright information

© 2020 Springer Nature Singapore Pte Ltd.

About this paper

Check for updates. Verify currency and authenticity via CrossMark

Cite this paper

Stasinos, C., Panas, A., Pantouvakis, JP., Ralli, P., Karagiannakidis, D. (2020). Investigation of the Earned Value Method (EVM) Applicability for Construction Operations Affected by the Learning Phenomenon. In: Panuwatwanich, K., Ko, CH. (eds) The 10th International Conference on Engineering, Project, and Production Management . Lecture Notes in Mechanical Engineering. Springer, Singapore. https://doi.org/10.1007/978-981-15-1910-9_20

Download citation

  • DOI: https://doi.org/10.1007/978-981-15-1910-9_20

  • Published:

  • Publisher Name: Springer, Singapore

  • Print ISBN: 978-981-15-1909-3

  • Online ISBN: 978-981-15-1910-9

  • eBook Packages: EngineeringEngineering (R0)

Publish with us

Policies and ethics