Scheduling Multi-Mode Projects under Uncertainty to Optimize Cash Flows: A Monte Carlo Ant Colony System Approach

  • Wei-Neng ChenEmail author
  • Jun Zhang
Regular Paper

Abstract

Project scheduling under uncertainty is a challenging field of research that has attracted increasing attention. While most existing studies only consider the single-mode project scheduling problem under uncertainty, this paper aims to deal with a more realistic model called the stochastic multi-mode resource constrained project scheduling problem with discounted cash flows (S-MRCPSPDCF). In the model, activity durations and costs are given by random variables. The objective is to find an optimal baseline schedule so that the expected net present value (NPV) of cash flows is maximized. To solve the problem, an ant colony system (ACS) based approach is designed. The algorithm dispatches a group of ants to build baseline schedules iteratively using pheromones and an expected discounted cost (EDC) heuristic. Since it is impossible to evaluate the expected NPV directly due to the presence of random variables, the algorithm adopts the Monte Carlo (MC) simulation technique. As the ACS algorithm only uses the best-so-far solution to update pheromone values, it is found that a rough simulation with a small number of random scenarios is enough for evaluation. Thus the computational cost is reduced. Experimental results on 33 instances demonstrate the effectiveness of the proposed model and the ACS approach.

Keywords

project scheduling optimization under uncertainty cash flow ant colony optimization Monte Carlo simulation 

Preview

Unable to display preview. Download preview PDF.

Unable to display preview. Download preview PDF.

Supplementary material

11390_2012_1276_MOESM1_ESM.docx (16 kb)
(DOC 15.7 kb)

References

  1. [1]
    Brucker P, Drexl A, Möhring R, Neumann K, Pesch E. Resource-constrained project scheduling: Notation, classification, models and methods. European Journal of Operational Research, 1999, 112(1): 3–41.zbMATHCrossRefGoogle Scholar
  2. [2]
    Blazewicz J, Lenstra J K, Rinnooy Kan A H G. Scheduling subject to resource constraints: Classification and complex. Discrete Applied Mathematics, 1983, 5(1): 11–24.MathSciNetzbMATHCrossRefGoogle Scholar
  3. [3]
    Ödamar L. A genetic algorithm approach to a general category project scheduling problem. IEEE Transactions on Systems, Man, and Cybernetics — Part C: Application and Reviews, 1999, 29(1): 44–59.CrossRefGoogle Scholar
  4. [4]
    Tseng L Y, Chen S C. Two-phase genetic local search algorithm for the multimode resource-constrained project scheduling problem. IEEE Transactions on Evolutionary Computation, 2009, 13(4): 848–857.MathSciNetCrossRefGoogle Scholar
  5. [5]
    Kolisch R. Project Scheduling under Resource Constraints: Efficient Heuristics for Several Problem Classes. Physica-Verlag, 1995.Google Scholar
  6. [6]
    Russell A H. Cash flows in networks. Management Science, 1970, 16(5): 357–373.zbMATHCrossRefGoogle Scholar
  7. [7]
    Herroelen W, De Reyck B, Demeulemeester E. Project network models with discounted cash flows: A guided tour through recent developments. European Journal of Operational Research, 1997, 100(1): 97–121.zbMATHCrossRefGoogle Scholar
  8. [8]
    Ulusoy G. Four payment models for the multi-mode resource constrained project scheduling problem with discounted cash flows. Annals of Operations Research, 2001, 102(1-4): 237–261.MathSciNetzbMATHCrossRefGoogle Scholar
  9. [9]
    Mika M, Waligóra G, Węglarz J. Simulated annealing and tabu search for multi-mode resource-constrained project scheduling with positive discounted cash flows and different payment models. European Journal of Operational Research, 2005, 164(3): 639–668.MathSciNetzbMATHCrossRefGoogle Scholar
  10. [10]
    Chen W N, Zhang J, Chung H S H, Huang R Z, Liu O. Optimizing discounted cash flows in project scheduling — An ant colony optimization approach. IEEE Transactions on Systems, Man, and Cybernetics — Part C: Applications and Reviews, 2010, 40(1): 64–77.CrossRefGoogle Scholar
  11. [11]
    Herroelen W, Leus R. Project scheduling under uncertainty: Survey and research potentials. European Journal of Operational Research, 2005, 165(2): 289–306.MathSciNetzbMATHCrossRefGoogle Scholar
  12. [12]
    Li Z, Ierapetritou M. Process scheduling under uncertainty: Review and challenges. Computers and Chemical Engineering, 2008, 32(4-5): 715–727.CrossRefGoogle Scholar
  13. [13]
    Sahinidis N V. Optimization under uncertainty: State-of-the-art and opportunities. Computers and Chemical Engineering, 2004, 28(6-7): 971–983.CrossRefGoogle Scholar
  14. [14]
    Park H K. Cash flow forecasting in construction project. KSCE Journal of Civil Engineering, 2004, 18(3): 265–271.CrossRefGoogle Scholar
  15. [15]
    Yang I T, Chang C Y. Stochastic resource-constrained scheduling for repetitive construction projects with uncertain supply of resources and funding. International Journal of Project Management, 2005, 23(7): 546–553.CrossRefGoogle Scholar
  16. [16]
    Wu X, Zhou X. Stochastic scheduling to minimize expected maximum lateness. European Journal of Operational Research, 2008, 190(1): 103–115.MathSciNetzbMATHCrossRefGoogle Scholar
  17. [17]
    Ke H, Liu B. Project scheduling problem with stochastic activity duration times. Applied Mathematics and Computation, 2005, 168(1): 342–353.MathSciNetzbMATHCrossRefGoogle Scholar
  18. [18]
    Guo Z X, Wong W X, Leung S Y S, Fan J T, Chan S F. Genetic optimization of order scheduling with multiple uncertainties. Expert Systems with Applications, 2008, 35(4): 1788–1801.CrossRefGoogle Scholar
  19. [19]
    Long L D, Ohsato A. Fuzzy critical chain method for project scheduling under resource constraints and uncertainty. International Journal of Project Management, 2008, 26(6): 688–698.CrossRefGoogle Scholar
  20. [20]
    Daniels R L, Carrillo J E. β-robust scheduling for single-machine systems with uncertain processing times. IIE Transactions, 1997, 29(11): 977–985.Google Scholar
  21. [21]
    Creemers S, Leus R, De Reyck B, Lambrecht M. Project scheduling for maximum NPV with variable activity durations and uncertain activity outcomes. In Proc. IEEE International Conference on Industrial Engineering and Engineering Management, Dec. 2008, pp.183–187.Google Scholar
  22. [22]
    Creemers S, Leus R, Lambrechts M. Scheduling Markovian PERT networks with maximum-NPV objective. Technical Report KBI 0811, Department of Decision Sciences and Information Management, KU Leuven, Belgium, 2008.Google Scholar
  23. [23]
    Sobel M J, Szmetekovsky J G, Tilson V. Scheduling projects with stochastic activity duration to maximize expected net present value. European Journal of Operational Research, 2009, 198(3): 697–705.MathSciNetzbMATHCrossRefGoogle Scholar
  24. [24]
    Wiesemann W, Kuhn D, Rustem B. Maximizing the net present value of a project under uncertainty. European Journal of Operational Research, 2010, 202(2): 356–367.MathSciNetzbMATHCrossRefGoogle Scholar
  25. [25]
    Szmerekovsky J G. Single machine scheduling under market uncertainty. European Journal of Operational Research, 2007, 177(1): 163–175.MathSciNetzbMATHCrossRefGoogle Scholar
  26. [26]
    Dorigo M, Maniezzo V, Colorni A. Ant system: Optimization by a colony of cooperating agents. IEEE Transactions on Systems, Man, and Cybernetics — Part B: Cybernetics, 1996, 26(1): 29–41.CrossRefGoogle Scholar
  27. [27]
    Dorigo M, Gambardella L M. Ant colony system: A cooperative learning approach to TSP. IEEE Transactions on Evolutionary Computation, 1997, 1(1): 53–66.CrossRefGoogle Scholar
  28. [28]
    Merkle D, Middendorf M, Schmeck H. Ant colony optimization for resource-constrained project scheduling. IEEE Transactions on Evolutionary Computation, 2002, 6(4): 333–346.CrossRefGoogle Scholar
  29. [29]
    Chen W N, Zhang J. An ant colony optimization approach to a grid workflow scheduling problem with various QoS requirements. IEEE Transactions on Systems, Man, and Cybernetics — Part C:Application and Reviews, 2009, 39(1): 29–43.CrossRefGoogle Scholar
  30. [30]
    Hu X M, Zhang J, Chung H S H, Liu O, Xiao J. An intelligent testing system embedded with an ant colony optimization based test composition method. IEEE Transactions on Systems, Man and Cybernetics — Part C:Application and Reviews, 2009, 39(6): 659–669.CrossRefGoogle Scholar
  31. [31]
    Gutjahr W J. S-ACO: An ant based approach to combinatorial optimization under uncertainty. In Proc. the 4th ANTS, Sept. 2004, pp.238–249.Google Scholar
  32. [32]
    Gutjahr W J. A converging ACO algorithm for stochastic combinatorial optimization. In Proc. the 2nd Symposium on Stochastic Algorithms, Foundations and Applications, Sept. 2003, pp.10–25.Google Scholar
  33. [33]
    Balaprakash P. Ant colony optimization under uncertainty. Technical Report No. TR/IRIDIA/2005-028, IRIDIA, Universite Libre de Bruxelles, 2005.Google Scholar
  34. [34]
    Brucker P, Knust S, Schoo A, Thiele O. A branch and bound algorithm for the resource-constrained project scheduling problem. European Journal of Operational Research, 1998, 107(2): 272–288.zbMATHCrossRefGoogle Scholar
  35. [35]
    Lee J K, Kim Y D. Search heuristics for resource constrained project scheduling. Journal of the Operational Research Society, 1996, 47(5): 678–689.zbMATHGoogle Scholar
  36. [36]
    Chiang C W, Huang Y Q, Wang W Y. Ant colony optimization with parameter adaptation for multi-mode resource-constrained project scheduling. Journal of Intelligent & Fuzzy Systems: Applications in Engineering and Technology, 2008, 19(4-5): 345–358.zbMATHGoogle Scholar
  37. [37]
    Józefowska J, Mika M, Różycki R, Waligóra G, Węglarz J. Simulated annealing for multi-mode resource-constrained project scheduling. Annals of Operations Research, 2001, 102(1-4): 137–155.MathSciNetzbMATHCrossRefGoogle Scholar
  38. [38]
    Bianchi L, Dorigo M, Gambardella L M, Gutjahr W J. Meta-heuristics in stochastic combinatorial optimization: A survey. Technical Report IDSIA-08-06, IDSIA, Dalle Molle Institute for Artificial Intelligence, 2006.Google Scholar
  39. [39]
    Bianchi L, Dorigo M, Gambardella L M, Gutjahr W J. A survey on metaheuristics for combinatorial optimization. Nat. Comput., 2009, 8(2): 239–287.MathSciNetzbMATHCrossRefGoogle Scholar
  40. [40]
    Jin Y, Branke J. Evolutionary optimization in uncertain environments A survey. IEEE Transactions on Evolutionary Computation, 2005, 9(3): 303–317.CrossRefGoogle Scholar
  41. [41]
    Vieira G E, Herrmann J W, Lin E. Rescheduling manufacturing systems: A framework of strategies, policies and methods. Journal of Scheduling, 2003, 6(1): 39–62.MathSciNetzbMATHCrossRefGoogle Scholar
  42. [42]
    Shtub A, Bard J F, Globerson S. Project Scheduling: Processes, Methodologies and Economics (2nd edition). Prentice Hall, 2002.Google Scholar
  43. [43]
    Kolisch R, Hartmann S. Heuristic algorithms for solving the resource-constrained project scheduling problem: Classification and computational analysis. In Handbook on Recent Advances in Project Scheduling. Weglarz J (ed), Dordrecht, The Netherlands: Kluwer Academic Publishers, 1999, pp.197–212.Google Scholar
  44. [44]
    Demeulemeester E, Dodin B, Herroelen W. A random activity network generator. Operations Research, 1993, 41(5): 972–980.zbMATHCrossRefGoogle Scholar

Copyright information

© Springer Science+Business Media New York & Science Press, China 2012

Authors and Affiliations

  1. 1.Department of Computer ScienceSun Yat-sen UniversityGuangzhouChina

Personalised recommendations