The discrete time/cost trade-off problem: extensions and heuristic procedures

  • Mario Vanhoucke
  • Dieter Debels
Article

Abstract

Time/cost trade-offs in project networks have been the subject of extensive research since the development of the critical path method (CPM) in the late 50s. Time/cost behaviour in a project activity basically describes the trade-off between the duration of the activity and its amount of non-renewable resources (e.g., money) committed to it. In the discrete version of the problem (the discrete time/cost trade-off problem), it is generally accepted that the trade-off follows a discrete non-increasing pattern, i.e., expediting an activity is possible by allocating more resources (i.e., at a larger cost) to it. However, due to its complexity, the problem has been solved for relatively small instances.

In this paper we elaborate on three extensions of the well-known discrete time/cost trade-off problem in order to cope with more realistic settings: time/switch constraints, work continuity constraints, and net present value maximization. We give an extensive literature overview of existing procedures for these problem types and discuss a new meta-heuristic approach in order to provide near-optimal heuristic solutions for the different problems. We present computational results for the problems under study by comparing the results for both exact and heuristic procedures. We demonstrate that the heuristic algorithms produce consistently good results for two versions of the discrete time/cost trade-off problem.

Keywords

Project scheduling Time/cost tradeoff Net present value 

Preview

Unable to display preview. Download preview PDF.

Unable to display preview. Download preview PDF.

References

  1. Akkan, C., Drexl, A., & Kimms, A. (2000a). Network decomposition for the discrete time/cost trade-off problem, part 1: models and bounding methods. In Proceedings of the seventh international workshop on project management and scheduling (pp. 29–31), Osnabrück, Germany, 17–19 April 2000. Google Scholar
  2. Akkan, C., Drexl, A., & Kimms, A. (2000b). Network decomposition for the discrete time/cost trade-off problem, part 2: network decomposition and computational results. In Proceedings of the seventh international workshop on project management and scheduling (pp. 32–34), Osnabrück, Germany, 17–19 April 2000. Google Scholar
  3. Bianco, L., & Speranza, M. G. (1990). Resource management in project scheduling. In Proceedings of the second international workshop on project management and scheduling, Compiègne, France, 20–22 June 1990. Google Scholar
  4. Billstein, N., & Radermacher, F. J. (1977). Time-cost optimization. Methods of Operations Research, 27, 274–294. Google Scholar
  5. Chen, Y. L., Rinks, D., & Tang, K. (1997). Critical path in an activity network with time constraints. European Journal of Operational Research, 100, 122–133. CrossRefGoogle Scholar
  6. Crowston, W. (1970). Network reduction and solution. Operations Research Quarterly, 21, 435–450. Google Scholar
  7. Crowston, W., & Thompson, G. L. (1967). Decision CPM: a method for simultaneous planning, scheduling and control of projects. Operations Research, 15, 407–426. Google Scholar
  8. De, P., Dunne, E. J., Ghosh, J. B., & Wells, C. E. (1995). The discrete time/cost trade-off problem revisited. European Journal of Operational Research, 81, 225–238. CrossRefGoogle Scholar
  9. De, P., Dunne, E. J., Ghosh, J. B., & Wells, C. E. (1997). Complexity of the discrete time/cost trade-off problem for project networks. Operations Research, 45, 302–306. Google Scholar
  10. De Boer, R. (1998). Resource-constrained multi-project manage- ment—a hierarchical decision support system. PhD dissertation, Institute for Business Engineering and Technology Application, The Netherlands. Google Scholar
  11. De Reyck, B., & Herroelen, W. (1996). On the use of the complexity index as a measure of complexity in activity networks. European Journal of Operational Research, 91, 347–366. CrossRefGoogle Scholar
  12. Deineko, V. G., & Woeginger, G. J. (2001). Hardness of approximation of the discrete time/cost trade-off problem. Operations Research Letters, 29, 207–210. CrossRefGoogle Scholar
  13. Demeulemeester, E., Elmaghraby, S. E., & Herroelen, W. (1996). Optimal procedures for the discrete time/cost trade-off problem in project networks. European Journal of Operational Research, 88, 50–68. CrossRefGoogle Scholar
  14. Demeulemeester, E., De Reyck, B., Foubert, B., Herroelen, W., & Vanhoucke, M. (1998). New computational results for the discrete time/cost trade-off problem in project networks. Journal of the Operational Research Society, 49, 1153–1163. CrossRefGoogle Scholar
  15. El-Rayes, K., & Moselhi, O. (1998). Resource-driven scheduling of repetitive activities. Construction Management and Economics, 16, 433–446. CrossRefGoogle Scholar
  16. Elmaghraby, S.E., & Herroelen, W. (1980). On the measurement of complexity in activity networks. European Journal of Operational Research, 5, 223–234. CrossRefGoogle Scholar
  17. Elmaghraby, S. E., & Kamburowski, J. (1992). The analysis of activity networks under generalized precedence relations. Management Science, 38, 1245–1263. Google Scholar
  18. Elmaghraby, S. E., & Salem, A. (1982). Optimal project compression under quadratic cost functions. Applications of Management Science, 2, 1–39. Google Scholar
  19. Elmaghraby, S. E., & Salem, A. (1984). Optimal linear approximation in project compression. IIE Transactions, 16(4), 339–347. CrossRefGoogle Scholar
  20. Erengüç, S. S., Tufekci, S., & Zappe, C. J. (1993). Solving time/cost trade-off problems with discounted cash flows using generalized Benders decomposition. Naval Research Logistics, 40, 25–50. CrossRefGoogle Scholar
  21. Falk, J. E., & Horowitz, J. L. (1972). Critical path problems with concave cost-time curves. Management Science, 19, 446–455. Google Scholar
  22. Ford, L. R., & Fulkerson, D. R. (1962). Flows in networks. New Jersey: Princeton University Press. Google Scholar
  23. Fulkerson, D. R. (1961). A network flow computation for project cost curves. Management Science, 7, 167–178. Google Scholar
  24. Glover, F. (1986). Future paths for integer programming and links to artificial intelligence. Computers and Operations Research, 5, 533–549. CrossRefGoogle Scholar
  25. Gong, D. (1997). Optimization of float use in risk analysis-based network scheduling. International Journal of Project Management, 15(3), 187–192. CrossRefGoogle Scholar
  26. Goto, E., Joko, T., Fujisawa, K., Katoh, N., & Furusaka, S. (2000). Maximizing net present value for generalized resource constrained project scheduling problem. Working paper Nomura Research Institute, Japan. Google Scholar
  27. Goyal, S. K. (1975). A note on the paper: a simple CPM time/cost trade-off algorithm. Management Science, 21, 718–722. Google Scholar
  28. Harris, R. B., & Ioannou, P. G. (1998). Scheduling projects with repeating activities. Journal of Construction Engineering and Management, 124(4), 269–278. CrossRefGoogle Scholar
  29. Herroelen, W., & De Reyck, B. (1999). Phase transitions in project scheduling. Journal of Operational Research Society, 50, 148–156. CrossRefGoogle Scholar
  30. Herroelen, W., Demeulemeester, E., & Van Dommelen, P. (1997). Project network models with discounted cash flows: A guided tour through recent developments. European Journal of Operational Research, 100, 97–121. CrossRefGoogle Scholar
  31. Herroelen, W., Demeulemeester, E., & De Reyck, B. (1999). A classification scheme for project scheduling problems. In J. Weglarz (Ed.), Handbook on recent advances in project scheduling (Chap. 1, pp. 1–26). Amsterdam: Kluwer Academic. Google Scholar
  32. Hindelang, T. J., & Muth, J. F. (1979). A dynamic programming algorithm for decision CPM networks. Operations Research, 27, 225–241. Google Scholar
  33. Kamburowski, J., Michael, D. J., & Stallmann, M. F. M. (1992). Optimal construction of project activity networks. In Proceedings of the 1992 annual meeting of the Decision Sciences Institute (pp. 1424–1426), San Francisco, USA. Google Scholar
  34. Kapur, K. C. (1973). An algorithm for the project cost/duration analysis problem with quadratic and convex cost functions. IIE Transactions, 5, 314–322. CrossRefGoogle Scholar
  35. Kelley, J. E. (1961). Critical path planning and scheduling: Mathematical basis. Operations Research, 9, 296–320. Google Scholar
  36. Kelley, J. E., & Walker, M. R. (1959). Critical path planning and scheduling: an introduction. Ambler: Mauchly Associates. Google Scholar
  37. Kolisch, R., Sprecher, A., & Drexl, A. (1995). Characterization and generation of a general class of resource-constrained project scheduling problems. Management Science, 41, 1693–1703. Google Scholar
  38. Lamberson, L. R., & Hocking, R. R. (1970). Optimum time compression in project scheduling. Management Science, 16, B-597–B-606. Google Scholar
  39. Moder, J. J., Phillips, C. R., & Davis, E. W. (1983). Project management with CPM, PERT and precedence diagramming (3rd ed.). New York: Van Nostrand Reinhold Company. Google Scholar
  40. Patterson, J. H., & Harvey, R. T. (1979). An implicit enumeration algorithm for the time/cost trade-off problem in project network analysis. Foundations of Control Engineering, 6, 107–117. Google Scholar
  41. Reda, R. M. (1990). RPM: repetitive project modelling. Journal of Construction Engineering and Management, 116(2), 316–330. Google Scholar
  42. Robinson, D. R. (1975). A dynamic programming solution to cost/time trade-off for CPM. Management Science, 22, 158–166. CrossRefGoogle Scholar
  43. Schrage, L. (1995). LINDO: Optimization software for linear programming. Chicago: LINDO Systems. Google Scholar
  44. Siemens, N. (1971). A simple CPM time/cost trade-off algorithm. Management Science, 17, B-354–B-363. Google Scholar
  45. Siemens, N., & Gooding, C. (1975). Reducing project duration at minimum cost: a time/cost trade-off algorithm. OMEGA, 3, 569–581. CrossRefGoogle Scholar
  46. Skutella, M. (1998). Approximation algorithms for the discrete time-cost trade-off problem. Mathematics of Operations Research, 23, 909–929. Google Scholar
  47. Vanhoucke, M. (2005). New computational results for the discrete time/cost trade-off problem with time-switch constraints. European Journal of Operational Research, 165, 359–374. CrossRefGoogle Scholar
  48. Vanhoucke, M. (2006). Work continuity constraints in project scheduling. Journal of Construction Engineering and Management, 132, 14–25. CrossRefGoogle Scholar
  49. Vanhoucke, M., Demeulemeester, E., & Herroelen, W. (2001). On maximizing the net present value of a project under renewable resource constraints. Management Science, 47, 1113–1121. CrossRefGoogle Scholar
  50. Vanhoucke, M., Demeulemeester, E., & Herroelen, W. (2002). Discrete time/cost trade-offs in project scheduling with time-switch constraints. Journal of the Operational Research Society, 53, 741–751. CrossRefGoogle Scholar
  51. Vercellis, C. (1990). Multi-project scheduling with time-resource-cost trade-offs: a tactical model. In Proceedings of the second international workshop on project management and scheduling, Compiègne, France, 20–22 June 1990. Google Scholar
  52. Wiest, J. D., & Levy, F. K. (1977). A management guide to PERT/CPM: with GERT/PDM/DCPM and other networks. New Jersey: Prentice-Hall. Google Scholar
  53. Yang, H. H., & Chen, Y. L. (2000). Finding the critical path in an activity network with time-switch constraints. European Journal of Operational Research, 120, 603–613. CrossRefGoogle Scholar

Copyright information

© Springer Science+Business Media, LLC 2007

Authors and Affiliations

  1. 1.Department of Management Information, Operations Management and Technology Policy, Faculty of Economics and Business AdministrationGhent UniversityGentBelgium
  2. 2.Operations and Technology Management CenterVlerick Leuven Gent Management SchoolGentBelgium

Personalised recommendations