The discrete time/cost trade-off problem: extensions and heuristic procedures

  • Published:
Journal of Scheduling Aims and scope Submit manuscript

Abstract

Time/cost trade-offs in project networks have been the subject of extensive research since the development of the critical path method (CPM) in the late 50s. Time/cost behaviour in a project activity basically describes the trade-off between the duration of the activity and its amount of non-renewable resources (e.g., money) committed to it. In the discrete version of the problem (the discrete time/cost trade-off problem), it is generally accepted that the trade-off follows a discrete non-increasing pattern, i.e., expediting an activity is possible by allocating more resources (i.e., at a larger cost) to it. However, due to its complexity, the problem has been solved for relatively small instances.

In this paper we elaborate on three extensions of the well-known discrete time/cost trade-off problem in order to cope with more realistic settings: time/switch constraints, work continuity constraints, and net present value maximization. We give an extensive literature overview of existing procedures for these problem types and discuss a new meta-heuristic approach in order to provide near-optimal heuristic solutions for the different problems. We present computational results for the problems under study by comparing the results for both exact and heuristic procedures. We demonstrate that the heuristic algorithms produce consistently good results for two versions of the discrete time/cost trade-off problem.

This is a preview of subscription content, log in via an institution to check access.

Access this article

Price excludes VAT (USA)
Tax calculation will be finalised during checkout.

Instant access to the full article PDF.

Institutional subscriptions

Similar content being viewed by others

References

  • Akkan, C., Drexl, A., & Kimms, A. (2000a). Network decomposition for the discrete time/cost trade-off problem, part 1: models and bounding methods. In Proceedings of the seventh international workshop on project management and scheduling (pp. 29–31), Osnabrück, Germany, 17–19 April 2000.

  • Akkan, C., Drexl, A., & Kimms, A. (2000b). Network decomposition for the discrete time/cost trade-off problem, part 2: network decomposition and computational results. In Proceedings of the seventh international workshop on project management and scheduling (pp. 32–34), Osnabrück, Germany, 17–19 April 2000.

  • Bianco, L., & Speranza, M. G. (1990). Resource management in project scheduling. In Proceedings of the second international workshop on project management and scheduling, Compiègne, France, 20–22 June 1990.

  • Billstein, N., & Radermacher, F. J. (1977). Time-cost optimization. Methods of Operations Research, 27, 274–294.

    Google Scholar 

  • Chen, Y. L., Rinks, D., & Tang, K. (1997). Critical path in an activity network with time constraints. European Journal of Operational Research, 100, 122–133.

    Article  Google Scholar 

  • Crowston, W. (1970). Network reduction and solution. Operations Research Quarterly, 21, 435–450.

    Google Scholar 

  • Crowston, W., & Thompson, G. L. (1967). Decision CPM: a method for simultaneous planning, scheduling and control of projects. Operations Research, 15, 407–426.

    Google Scholar 

  • De, P., Dunne, E. J., Ghosh, J. B., & Wells, C. E. (1995). The discrete time/cost trade-off problem revisited. European Journal of Operational Research, 81, 225–238.

    Article  Google Scholar 

  • De, P., Dunne, E. J., Ghosh, J. B., & Wells, C. E. (1997). Complexity of the discrete time/cost trade-off problem for project networks. Operations Research, 45, 302–306.

    Google Scholar 

  • De Boer, R. (1998). Resource-constrained multi-project manage- ment—a hierarchical decision support system. PhD dissertation, Institute for Business Engineering and Technology Application, The Netherlands.

  • De Reyck, B., & Herroelen, W. (1996). On the use of the complexity index as a measure of complexity in activity networks. European Journal of Operational Research, 91, 347–366.

    Article  Google Scholar 

  • Deineko, V. G., & Woeginger, G. J. (2001). Hardness of approximation of the discrete time/cost trade-off problem. Operations Research Letters, 29, 207–210.

    Article  Google Scholar 

  • Demeulemeester, E., Elmaghraby, S. E., & Herroelen, W. (1996). Optimal procedures for the discrete time/cost trade-off problem in project networks. European Journal of Operational Research, 88, 50–68.

    Article  Google Scholar 

  • Demeulemeester, E., De Reyck, B., Foubert, B., Herroelen, W., & Vanhoucke, M. (1998). New computational results for the discrete time/cost trade-off problem in project networks. Journal of the Operational Research Society, 49, 1153–1163.

    Article  Google Scholar 

  • El-Rayes, K., & Moselhi, O. (1998). Resource-driven scheduling of repetitive activities. Construction Management and Economics, 16, 433–446.

    Article  Google Scholar 

  • Elmaghraby, S.E., & Herroelen, W. (1980). On the measurement of complexity in activity networks. European Journal of Operational Research, 5, 223–234.

    Article  Google Scholar 

  • Elmaghraby, S. E., & Kamburowski, J. (1992). The analysis of activity networks under generalized precedence relations. Management Science, 38, 1245–1263.

    Google Scholar 

  • Elmaghraby, S. E., & Salem, A. (1982). Optimal project compression under quadratic cost functions. Applications of Management Science, 2, 1–39.

    Google Scholar 

  • Elmaghraby, S. E., & Salem, A. (1984). Optimal linear approximation in project compression. IIE Transactions, 16(4), 339–347.

    Article  Google Scholar 

  • Erengüç, S. S., Tufekci, S., & Zappe, C. J. (1993). Solving time/cost trade-off problems with discounted cash flows using generalized Benders decomposition. Naval Research Logistics, 40, 25–50.

    Article  Google Scholar 

  • Falk, J. E., & Horowitz, J. L. (1972). Critical path problems with concave cost-time curves. Management Science, 19, 446–455.

    Google Scholar 

  • Ford, L. R., & Fulkerson, D. R. (1962). Flows in networks. New Jersey: Princeton University Press.

    Google Scholar 

  • Fulkerson, D. R. (1961). A network flow computation for project cost curves. Management Science, 7, 167–178.

    Google Scholar 

  • Glover, F. (1986). Future paths for integer programming and links to artificial intelligence. Computers and Operations Research, 5, 533–549.

    Article  Google Scholar 

  • Gong, D. (1997). Optimization of float use in risk analysis-based network scheduling. International Journal of Project Management, 15(3), 187–192.

    Article  Google Scholar 

  • Goto, E., Joko, T., Fujisawa, K., Katoh, N., & Furusaka, S. (2000). Maximizing net present value for generalized resource constrained project scheduling problem. Working paper Nomura Research Institute, Japan.

  • Goyal, S. K. (1975). A note on the paper: a simple CPM time/cost trade-off algorithm. Management Science, 21, 718–722.

    Google Scholar 

  • Harris, R. B., & Ioannou, P. G. (1998). Scheduling projects with repeating activities. Journal of Construction Engineering and Management, 124(4), 269–278.

    Article  Google Scholar 

  • Herroelen, W., & De Reyck, B. (1999). Phase transitions in project scheduling. Journal of Operational Research Society, 50, 148–156.

    Article  Google Scholar 

  • Herroelen, W., Demeulemeester, E., & Van Dommelen, P. (1997). Project network models with discounted cash flows: A guided tour through recent developments. European Journal of Operational Research, 100, 97–121.

    Article  Google Scholar 

  • Herroelen, W., Demeulemeester, E., & De Reyck, B. (1999). A classification scheme for project scheduling problems. In J. Weglarz (Ed.), Handbook on recent advances in project scheduling (Chap. 1, pp. 1–26). Amsterdam: Kluwer Academic.

    Google Scholar 

  • Hindelang, T. J., & Muth, J. F. (1979). A dynamic programming algorithm for decision CPM networks. Operations Research, 27, 225–241.

    Google Scholar 

  • Kamburowski, J., Michael, D. J., & Stallmann, M. F. M. (1992). Optimal construction of project activity networks. In Proceedings of the 1992 annual meeting of the Decision Sciences Institute (pp. 1424–1426), San Francisco, USA.

  • Kapur, K. C. (1973). An algorithm for the project cost/duration analysis problem with quadratic and convex cost functions. IIE Transactions, 5, 314–322.

    Article  Google Scholar 

  • Kelley, J. E. (1961). Critical path planning and scheduling: Mathematical basis. Operations Research, 9, 296–320.

    Google Scholar 

  • Kelley, J. E., & Walker, M. R. (1959). Critical path planning and scheduling: an introduction. Ambler: Mauchly Associates.

    Google Scholar 

  • Kolisch, R., Sprecher, A., & Drexl, A. (1995). Characterization and generation of a general class of resource-constrained project scheduling problems. Management Science, 41, 1693–1703.

    Google Scholar 

  • Lamberson, L. R., & Hocking, R. R. (1970). Optimum time compression in project scheduling. Management Science, 16, B-597–B-606.

    Google Scholar 

  • Moder, J. J., Phillips, C. R., & Davis, E. W. (1983). Project management with CPM, PERT and precedence diagramming (3rd ed.). New York: Van Nostrand Reinhold Company.

    Google Scholar 

  • Patterson, J. H., & Harvey, R. T. (1979). An implicit enumeration algorithm for the time/cost trade-off problem in project network analysis. Foundations of Control Engineering, 6, 107–117.

    Google Scholar 

  • Reda, R. M. (1990). RPM: repetitive project modelling. Journal of Construction Engineering and Management, 116(2), 316–330.

    Google Scholar 

  • Robinson, D. R. (1975). A dynamic programming solution to cost/time trade-off for CPM. Management Science, 22, 158–166.

    Article  Google Scholar 

  • Schrage, L. (1995). LINDO: Optimization software for linear programming. Chicago: LINDO Systems.

    Google Scholar 

  • Siemens, N. (1971). A simple CPM time/cost trade-off algorithm. Management Science, 17, B-354–B-363.

    Google Scholar 

  • Siemens, N., & Gooding, C. (1975). Reducing project duration at minimum cost: a time/cost trade-off algorithm. OMEGA, 3, 569–581.

    Article  Google Scholar 

  • Skutella, M. (1998). Approximation algorithms for the discrete time-cost trade-off problem. Mathematics of Operations Research, 23, 909–929.

    Google Scholar 

  • Vanhoucke, M. (2005). New computational results for the discrete time/cost trade-off problem with time-switch constraints. European Journal of Operational Research, 165, 359–374.

    Article  Google Scholar 

  • Vanhoucke, M. (2006). Work continuity constraints in project scheduling. Journal of Construction Engineering and Management, 132, 14–25.

    Article  Google Scholar 

  • Vanhoucke, M., Demeulemeester, E., & Herroelen, W. (2001). On maximizing the net present value of a project under renewable resource constraints. Management Science, 47, 1113–1121.

    Article  Google Scholar 

  • Vanhoucke, M., Demeulemeester, E., & Herroelen, W. (2002). Discrete time/cost trade-offs in project scheduling with time-switch constraints. Journal of the Operational Research Society, 53, 741–751.

    Article  Google Scholar 

  • Vercellis, C. (1990). Multi-project scheduling with time-resource-cost trade-offs: a tactical model. In Proceedings of the second international workshop on project management and scheduling, Compiègne, France, 20–22 June 1990.

  • Wiest, J. D., & Levy, F. K. (1977). A management guide to PERT/CPM: with GERT/PDM/DCPM and other networks. New Jersey: Prentice-Hall.

    Google Scholar 

  • Yang, H. H., & Chen, Y. L. (2000). Finding the critical path in an activity network with time-switch constraints. European Journal of Operational Research, 120, 603–613.

    Article  Google Scholar 

Download references

Author information

Authors and Affiliations

Authors

Corresponding author

Correspondence to Mario Vanhoucke.

Rights and permissions

Reprints and permissions

About this article

Cite this article

Vanhoucke, M., Debels, D. The discrete time/cost trade-off problem: extensions and heuristic procedures. J Sched 10, 311–326 (2007). https://doi.org/10.1007/s10951-007-0031-y

Download citation

  • Published:

  • Issue Date:

  • DOI: https://doi.org/10.1007/s10951-007-0031-y

Keywords

Navigation