EPB tunneling challenges in bouldery ground: a new experience on the Tabriz metro line 1, Iran

  • Original Paper
  • Published:
Bulletin of Engineering Geology and the Environment Aims and scope Submit manuscript

Abstract

Underground construction of the Tabriz metro line 1 involved boring twin tunnels with two earth pressure balance machines in alluvial deposits. Although this type of machine is recommended for excavation in fine soils, its performance was evaluated in this project where part of the ground consists of alluvial deposits with particle size ranging from silt to boulder and even rock blocks. It was found that the tunnel boring machine (TBM) performance was highly reduced due to the variation in ground conditions. Many types of problem were observed during the excavation in coarse grained alluvial deposits including high cutter-head torque, excessive wear of tools, breaking of TBM parts and ground instabilities in the form of large settlement and ground collapse. A trial effort was implanted to stabilize the overburden ground by the injection of cement grout, but this proved to be unsuccessful. In both cases, the excavation operation was delayed. With the experience gained from the excavation of the first tunnel and use of foam with a high foam expansion ratio as a soil conditioner in closed mode, the performance of the TBM in the second tunnel improved.

This is a preview of subscription content, log in via an institution to check access.

Access this article

Price excludes VAT (USA)
Tax calculation will be finalised during checkout.

Instant access to the full article PDF.

Institutional subscriptions

Fig. 1
Fig. 2
Fig. 3
Fig. 4
Fig. 5
Fig. 6
Fig. 7
Fig. 8
Fig. 9
Fig. 10
Fig. 11
Fig. 12
Fig. 13
Fig. 14
Fig. 15
Fig. 16
Fig. 17
Fig. 18
Fig. 19
Fig. 20
Fig. 21

Similar content being viewed by others

References

  • Carrieri G, Fornari E, Guglielmetti V, Crova R (2006) Torino metro line 1: use of three TBM-EPBs in very coarse grained soil. Tunn Undergr Space Technol 21:274–275

    Article  Google Scholar 

  • Centis S, Giacomin G (2004) EPB tunneling in highly variable ground, the experience of Oporto light metro. Tunn Undergr Space Technol 19:358

    Article  Google Scholar 

  • Ewert FK (1985) Rock grouting with emphasis on dam sites. Springer, Berlin 428

    Book  Google Scholar 

  • Festl J (2006) The LCPC test: a possibility to determine soil abrasivity? Bachelor thesis, Technical University of Munchen

  • Hessami K, Pantosti D, Tabasi H, Shabanian E, Abbasi MR, Feghhi K, Solymani S (2003) Paleo-earthquakes and slip rates of the North Tabriz Fault, NW Iran: preliminary results. Ann Geophys 46(5):903–915

    Google Scholar 

  • Noppadol P, Attasit S, Sahapol T, Sippavut T (2006) Characteristics of ground movement from shield tunneling of the first Bangkok Subway line. In: Proceedings of the international symposium on underground excavation and tunneling, Bangkok Thailand, pp 104–116

  • Skjeggedal T, Holter KG (1998) Six case histories. Norwegian TBM tunneling, 30 Years of experience with TBMs in Norwegian tunneling. Nor Soil Rock Eng Assoc 11:79–84

    Google Scholar 

  • Thuro K (1997) Drillability prediction-geological influences in hard rock drill and blast tunneling. Geol Rundsch 86:426–438

    Article  Google Scholar 

  • Thuro K, Käsling H (2009) Classification of the abrasiveness of soil and rock/Klassifikation der Abrasivität von Boden und Fels. Geomech Tunn 2:179–188

    Article  Google Scholar 

  • Zhao J, Gong QM, Eisensten Z (2006) Tunneling through a frequently changing and mixed ground: a case history in Singapore. Tunn Undergr Space Technol 22:388–400

    Article  Google Scholar 

Download references

Acknowledgments

The authors would like to expresses their special thanks to Tabriz Urban Railway Organization (TURO) and Gueno consultant engineers for allowing these data obtained in the tunneling site to be published.

Author information

Authors and Affiliations

Authors

Corresponding author

Correspondence to Ali Uromeihy.

Rights and permissions

Reprints and permissions

About this article

Cite this article

Barzegari, G., Uromeihy, A. & Zhao, J. EPB tunneling challenges in bouldery ground: a new experience on the Tabriz metro line 1, Iran. Bull Eng Geol Environ 73, 429–440 (2014). https://doi.org/10.1007/s10064-013-0490-7

Download citation

  • Received:

  • Accepted:

  • Published:

  • Issue Date:

  • DOI: https://doi.org/10.1007/s10064-013-0490-7

Keywords

Navigation