Abstract
Underground construction of the Tabriz metro line 1 involved boring twin tunnels with two earth pressure balance machines in alluvial deposits. Although this type of machine is recommended for excavation in fine soils, its performance was evaluated in this project where part of the ground consists of alluvial deposits with particle size ranging from silt to boulder and even rock blocks. It was found that the tunnel boring machine (TBM) performance was highly reduced due to the variation in ground conditions. Many types of problem were observed during the excavation in coarse grained alluvial deposits including high cutter-head torque, excessive wear of tools, breaking of TBM parts and ground instabilities in the form of large settlement and ground collapse. A trial effort was implanted to stabilize the overburden ground by the injection of cement grout, but this proved to be unsuccessful. In both cases, the excavation operation was delayed. With the experience gained from the excavation of the first tunnel and use of foam with a high foam expansion ratio as a soil conditioner in closed mode, the performance of the TBM in the second tunnel improved.
Similar content being viewed by others
References
Carrieri G, Fornari E, Guglielmetti V, Crova R (2006) Torino metro line 1: use of three TBM-EPBs in very coarse grained soil. Tunn Undergr Space Technol 21:274–275
Centis S, Giacomin G (2004) EPB tunneling in highly variable ground, the experience of Oporto light metro. Tunn Undergr Space Technol 19:358
Ewert FK (1985) Rock grouting with emphasis on dam sites. Springer, Berlin 428
Festl J (2006) The LCPC test: a possibility to determine soil abrasivity? Bachelor thesis, Technical University of Munchen
Hessami K, Pantosti D, Tabasi H, Shabanian E, Abbasi MR, Feghhi K, Solymani S (2003) Paleo-earthquakes and slip rates of the North Tabriz Fault, NW Iran: preliminary results. Ann Geophys 46(5):903–915
Noppadol P, Attasit S, Sahapol T, Sippavut T (2006) Characteristics of ground movement from shield tunneling of the first Bangkok Subway line. In: Proceedings of the international symposium on underground excavation and tunneling, Bangkok Thailand, pp 104–116
Skjeggedal T, Holter KG (1998) Six case histories. Norwegian TBM tunneling, 30 Years of experience with TBMs in Norwegian tunneling. Nor Soil Rock Eng Assoc 11:79–84
Thuro K (1997) Drillability prediction-geological influences in hard rock drill and blast tunneling. Geol Rundsch 86:426–438
Thuro K, Käsling H (2009) Classification of the abrasiveness of soil and rock/Klassifikation der Abrasivität von Boden und Fels. Geomech Tunn 2:179–188
Zhao J, Gong QM, Eisensten Z (2006) Tunneling through a frequently changing and mixed ground: a case history in Singapore. Tunn Undergr Space Technol 22:388–400
Acknowledgments
The authors would like to expresses their special thanks to Tabriz Urban Railway Organization (TURO) and Gueno consultant engineers for allowing these data obtained in the tunneling site to be published.
Author information
Authors and Affiliations
Corresponding author
Rights and permissions
About this article
Cite this article
Barzegari, G., Uromeihy, A. & Zhao, J. EPB tunneling challenges in bouldery ground: a new experience on the Tabriz metro line 1, Iran. Bull Eng Geol Environ 73, 429–440 (2014). https://doi.org/10.1007/s10064-013-0490-7
Received:
Accepted:
Published:
Issue Date:
DOI: https://doi.org/10.1007/s10064-013-0490-7