Transformer testing is an indispensable procedure to guarantee that transformers are fulfilling all requirements and guaranteed values. After completed FAT (Factory Acceptance Test), to proof the transformer design, site commissioning test shall be performed to detect potential transport damages or faults at site installation before energizing the transformer.

As a minimum requirement, we recommend to perform a dissipation factor (\(\tan\delta\))-, TTR (Transformer Turns Ratio)-, insulation resistance-, ohmic resistance and SFRA (Sweep Frequency Response Analysis) measurement for conventional transformers as site tests.

Depending on circumstances, various additional tests can be performed according to customer requirements. For transformer or reactor site works, the installation time might be critical (e.g. outage time of a power plant) but can be planned in advance. In case of an emergency, the time between failure and energizing the replacement unit is crucial. But also under time pressure, to dispense on site test is saving on the wrong place, and may lead to huge technical damages and monetary losses.

A different approach to overcome a long installation and commissioning time are multi ratio and lightweight single phase transformers filled with environmental friendly synthetic ester, which can be transported without any special transport permits. This has also been proven at a demonstration run where it took just 30 working hours within three working days, to install, test and energize a 345 kV transformer bank, three 1-phase units each 100 MVA, which worked then in regular network operation including overload conditions.

We give some recommendation about the required site tests, due to the fact that these transformers are more complex compared to conventional transformers. The higher complexity is justified by the fact that the resilience transformers are covering many different transformer designs and can be installed very flexible in the shortest possible time on site.

This is a preview of subscription content, log in via an institution to check access.

Access this article

Price excludes VAT (USA)
Tax calculation will be finalised during checkout.

Instant access to the full article PDF.

Institutional subscriptions

Fig. 1.
Fig. 2.
Fig. 3.
Fig. 4.
Fig. 5.
Fig. 6.

Similar content being viewed by others

Notes

  1. PRETACT®, MIDEL® and Nomex® are registered trademarks.

References

  1. IPCC: Fifth assessment report, AR5. http://www.ipcc.ch/report/ar5/wg1/.

  2. McCracken, K. G., Dreschhoff, G. A. M., Zeller, E. J., Smart, D. F., Shea, M. A. (2001): Solar cosmic ray events for the period 1561–1994: 1. Identification in polar ice, 1561–1950. J. Geophys. Res. 106, 21585–21598.

    Article  Google Scholar 

  3. Pukel, G. J., Fleck, G., Pregartner, H., Fritsche, R. (2016): Safe and environmentally friendly large power transformers with ester successful introduction of ester liquids at the 420 kV transmission level. In IEEE electrical insulation conference (EIC), Montreal, Canada, 19–22 June 2016.

    Google Scholar 

  4. IEEE Std C57.154TM-2012: IEEE standard for the design, testing, and application of liquid-immersed distribution, power, and regulating transformers using high-temperature insulation systems and operating at elevated temperatures.

  5. Mendes, Dr. J. C., Marcondes, R. A., Nakamura, J. (2004): On-site tests on HV power transformers. In CIGRE A2-211, Paris.

    Google Scholar 

Download references

Author information

Authors and Affiliations

Authors

Corresponding author

Correspondence to Stefan Riegler.

Additional information

Paper submitted for the CIGRE Session 2018, SC A2, Paris, France, August 26–31, 2018.

Rights and permissions

Reprints and permissions

About this article

Check for updates. Verify currency and authenticity via CrossMark

Cite this article

Riegler, S., Schweiger, E., Ettl, C. et al. Recommendation of site commissioning tests for rapid recovery transformers with an installation time less than 30 hours. Elektrotech. Inftech. 135, 543–547 (2018). https://doi.org/10.1007/s00502-018-0669-5

Download citation

  • Published:

  • Issue Date:

  • DOI: https://doi.org/10.1007/s00502-018-0669-5

Keywords

Navigation