Scheduling of repetitive construction projects using geographic information systems: an integration of critical path method and line of balance

  • Anjul TomarEmail author
  • V. K. Bansal
Original Paper
  • 6 Downloads

Abstract

Critical path method (CPM) is the widely used technique for scheduling of non-repetitive construction projects, on the other hand, line of balance (LOB) is used for scheduling of repetitive construction projects. There may exist repetitive and non-repetitive parts together in a construction project. In the present study, to schedule repetitive and non-repetitive parts of a construction project together, CPM and LOB techniques have been integrated within the geographic information systems (GIS) environment. The scheduling tool has been developed in which activities of a repetitive part are scheduled using CPM and different repetitive parts are scheduled using LOB. A sample project scheduled using CPM technique takes 520 days, however, if the same project is scheduled using the developed tool takes 214 days. Further, construction planning is not done in isolation, that is, without considering surroundings of a construction project under consideration. The scheduling tool developed in GIS environment considers the effect of surroundings on the developed integrated schedule. A link has been established between the activities of the developed schedule and corresponding 3D components in GIS environment to develop 4D model of execution sequence of a construction project. This facilitates in checking logical errors, resource continuity, and incompleteness of the developed integrated schedule.

Keywords

Repetitive construction Construction planning Construction scheduling GIS LOB 

Notes

Compliance with ethical standards

Conflict of interest

All authors declare that they have no conflict of interest.

References

  1. Agrama, F. A. E. M. (2011). Linear projects scheduling using spreadsheets features. Alexandria Engineering Journal, 50(2), 179–185.CrossRefGoogle Scholar
  2. Ali, M. M., & Elazouni, A. (2009). Finance-based CPM/LOB scheduling of projects with repetitive non-serial activities. Construction management and economics, 27(9), 839–856.CrossRefGoogle Scholar
  3. Ammar, M. A. (2012). LOB and CPM integrated method for scheduling repetitive projects. Journal of construction engineering and management, 139(1), 44–50.CrossRefGoogle Scholar
  4. Ammar, M. A., & Abdel-Maged, A. F. (2018). Modeling of LOB scheduling with learning development effect. International Journal of Construction Management, 18(6), 517–526.CrossRefGoogle Scholar
  5. Arditi, D., & Albulak, M. Z. (1986). Line-of-balance scheduling in pavement construction. Journal of Construction Engineering and Management, 112(3), 411–424.CrossRefGoogle Scholar
  6. Aziz, R. F. (2013). Optimizing strategy for repetitive construction projects within multi-mode resources. Alexandria Engineering Journal, 52(1), 67–81.CrossRefGoogle Scholar
  7. Bansal, V. K. (2015). Potential application areas of GIS in preconstruction planning. Journal of Professional Issues in Engineering Education and Practice, 142(1), 06015002.CrossRefGoogle Scholar
  8. Bansal, V. K. (2017). Integrated CAD and GIS–based framework to support construction planning: Case study. Journal of Architectural Engineering, 23(3), 05017005.CrossRefGoogle Scholar
  9. Bansal, V. K., & Pal, M. (2008). Generating, evaluating, and visualizing construction schedule with geographic information systems. Journal of Computing in Civil Engineering, 22(4), 233–242.CrossRefGoogle Scholar
  10. Carr, R. I., & Meyer, W. L. (1974). Planning construction of repetitive building units. Journal of the Construction Division, 100(3), 403–412.Google Scholar
  11. Cho, K., Hong, T., & Hyun, C. (2010). Scheduling model for repetitive construction processes for high-rise buildings. Canadian Journal of Civil Engineering, 38(1), 36–48.CrossRefGoogle Scholar
  12. Chrzanowski, E. N., & Johnston, D. W. (1986). Application of linear scheduling. Journal of Construction Engineering and Management, 112(4), 476–491.CrossRefGoogle Scholar
  13. Chu, M., Matthews, J., & Love, P. E. (2018). Integrating mobile building information modelling and augmented reality systems: an experimental study. Automation in Construction, 85, 305–316.CrossRefGoogle Scholar
  14. Damci, A., Arditi, D., & Polat, G. (2013a). Multiresource leveling in line-of-balance scheduling. Journal of Construction Engineering and Management, 139(9), 1108–1116.CrossRefGoogle Scholar
  15. Damci, A., Arditi, D., & Polat, G. (2013b). Resource leveling in line-of-balance scheduling. Computer-Aided Civil and Infrastructure Engineering, 28(9), 679–692.CrossRefGoogle Scholar
  16. Damci, A., Arditi, D., & Polat, G. (2016). Impacts of different objective functions on resource leveling in Line-of-Balance scheduling. KSCE Journal of Civil Engineering, 20(1), 58–67.CrossRefGoogle Scholar
  17. Fan, S. L., & Tserng, H. P. (2006). Object-oriented scheduling for repetitive projects with soft logics. Journal of Construction Engineering and management, 132(1), 35–48.CrossRefGoogle Scholar
  18. Haque, M. E., & Rahman, M. (2009). Time-space-activity conflict detection using 4D visualization in multi-storied construction project. In: H. Badioze Zaman, P. Robinson, M. Petrou, P. Olivier, H. Schröder, T.K. Shih (Ed.), Visual informatics: bridging research and practice. IVIC 2009. Lecture notes in computer science, (vol 5857, pp.266–278). Berlin, Heidelberg: Springer.CrossRefGoogle Scholar
  19. Harris, R. B., & Ioannou, P. G. (1998). Scheduling projects with repeating activities. Journal of Construction Engineering and Management, 124(4), 269–278.CrossRefGoogle Scholar
  20. Hegazy, T., & Kamarah, E. (2008). Efficient repetitive scheduling for high-rise construction. Journal of construction engineering and management, 134(4), 253–264.CrossRefGoogle Scholar
  21. Hegazy, T., & Wassef, N. (2001). Cost optimization in projects with repetitive nonserial activities. Journal of Construction Engineering and Management, 127(3), 183–191.CrossRefGoogle Scholar
  22. Hu, Z., & Zhang, J. (2011). BIM-and 4D-based integrated solution of analysis and management for conflicts and structural safety problems during construction: 2. Development and site trials. Automation in Construction, 20(2), 167–180.Google Scholar
  23. Ioannou, P. G., & Yang, I. T. (2016). Repetitive scheduling method: Requirements, modeling, and implementation. Journal of Construction Engineering and Management, 142(5), 04016002.CrossRefGoogle Scholar
  24. Johnston, D. W. (1981). Linear scheduling method for highway construction. Journal of the Construction Division, 107(2), 247–261.Google Scholar
  25. Kenley, R., & Seppänen, O. (2009). Location based management of construction projects: part of a new typology for project scheduling methodologies. In Proceedings of the 2009 winter simulation conference (pp. 2563–2570). Austin, TX, USA: IEEE.CrossRefGoogle Scholar
  26. Li, X., Yi, W., Chi, H. L., Wang, X., & Chan, A. P. (2018). A critical review of virtual and augmented reality (VR/AR) applications in construction safety. Automation in Construction, 86, 150–162.CrossRefGoogle Scholar
  27. Moder, J. J., Phillips, C. R., & Davis, E. W. (1983). Project management with CPM, PERT and project diagramming. 3rd edn. New York: Van Nostrand Reinhold.Google Scholar
  28. Moon, H., Dawood, N., & Kang, L. (2014). Development of workspace conflict visualization system using 4D object of work schedule. Advanced Engineering Informatics, 28(1), 50–65.CrossRefGoogle Scholar
  29. Nadeem, A., Wong, A. K. D., Akhanova, G., Azhar, S., and Wong, S. N. (2018). Application of Building Information Modeling (BIM) in Site Management-Material and Progress Control. In Proceedings of the 21st International Symposium on Advancement of Construction Management and Real Estate (pp. 289–297). Springer, Singapore.CrossRefGoogle Scholar
  30. Nguyen, C. H. P., & Choi, Y. (2018). Comparison of point cloud data and 3D CAD data for on-site dimensional inspection of industrial plant piping systems. Automation in Construction, 91, 44–52.CrossRefGoogle Scholar
  31. O'Brien, J. J. (1975). VPM scheduling for high-rise buildings. Journal of the Construction Division, 101(4), 895–905.Google Scholar
  32. O’Brien, J. (1971). CPM in construction management. New York: McGraw-Hill Publishing Company.Google Scholar
  33. Reda, R. M. (1990). RPM: Repetitive project modeling. Journal of Construction Engineering and Management, 116(2), 316–330.CrossRefGoogle Scholar
  34. Russell, A., Staub-French, S., Tran, N., & Wong, W. (2009). Visualizing high-rise building construction strategies using linear scheduling and 4D CAD. Automation in Construction, 18(2), 219–236.CrossRefGoogle Scholar
  35. Selinger, S. (1980). Construction planning for linear projects. Journal of the Construction Division, ASCE, 106, 195–205.Google Scholar
  36. Sharma, S., & Bansal, V. K. (2018). Location-based planning and scheduling of highway construction projects in hilly terrain using GIS. Canadian Journal of Civil Engineering, 45(7), 570–582.CrossRefGoogle Scholar
  37. Sharma, S., Bansal, V. K., & Parti, R. (2016). Location-based highway construction planning using geographic information systems. International Journal of Construction Management, 16(4), 299–314.CrossRefGoogle Scholar
  38. Su, Y., & Lucko, G. (2015). Comparison and renaissance of classic line-of-balance and linear schedule concepts for construction industry. Organization, technology & management in construction: an international journal, 7(2), 1315–1329.CrossRefGoogle Scholar
  39. Suhail, S. A., & Neale, R. H. (1994). CPM/LOB: New methodology to integrate CPM and line of balance. Journal of Construction Engineering and Management, 120(3), 667–684.CrossRefGoogle Scholar
  40. Vorster, M. C., Beliveau, Y. J., & Bafna, T. (1992). Linear scheduling and visualization. Transportation Research Record, 1351, 32–39.Google Scholar
  41. Wu, I., and Chiu, Y. (2010). 4D Workspace conflict detection and analysis system. In Proceedings of the 10th International Conference on Construction Applications of Virtual Reality. Japan.Google Scholar
  42. Zahran, K., Nour, M., & Hosny, O. (2016). The effect of learning on line of balance scheduling: Obstacles and potentials. International Journal of Engineering Science, 6(4), 3831–3841.Google Scholar
  43. Zhang, L., Tang, Y., & Qi, J. (2017). Resource leveling based on backward bontrolling activity in line of balance. Mathematical Problems in Engineering, 2017, 7545980.  https://doi.org/10.1155/2017/7545980.Google Scholar

Copyright information

© Springer Nature Switzerland AG 2019

Authors and Affiliations

  1. 1.Department of Civil EngineeringNational Institute of Technology HamirpurHamirpurIndia

Personalised recommendations