Methodology for Estimating the Cost of Delay in Architectural Engineering Projects: Case of Metro Rails in India

  • Yash Kumar MittalEmail author
  • Virendra Kumar Paul
  • Anil Sawhney
Original Contribution
  • 53 Downloads

Abstract

Development of a nation is directly related to the accomplishment of public infrastructure projects. They cater to the objectives of sector-specific demand and accrue benefits in other related fields. These architectural engineering projects contribute to the overall development, which is complex to measure in tangible terms alone, but call for establishing indicators for measuring intangible benefits as well. Delay in projects is considered to affect the tangible cost benefits. It is, however, a limited perception of delay consequences. The cost of delay (CoD), therefore, can be determined by considering the overall impact of tangible and intangible benefits of such projects. This paper brings out the framework for determining the CoD for the selected case study of a metro rail project. It reflects the consequences of delay in overall development prospects and high-level infrastructure objectives by establishing the CoD. The cost thus established can serve as the basis for mobilizing additional resources and strategic decision making in the best interest of overall benefits. The outcome of the study creates an opportunity to manage metro rail projects by mitigating the negative consequences of time overruns.

Keywords

Public infrastructure projects Architectural engineering Metro rail projects Project delay Cost benefits Cost of delay 

Notes

Supplementary material

40030_2019_366_MOESM1_ESM.docx (46 kb)
Supplementary material 1 (DOCX 47 kb)

References

  1. 1.
    P. Patanakul, Y.H. Kwak, O. Zwikael, M. Liu, What impacts the performance of large-scale government projects? Int. J. Proj. Manag. 34(3), 452–466 (2016)CrossRefGoogle Scholar
  2. 2.
    S. Wells, C. Bullen, A near miss: the importance of context in a public health informatics project in a New Zealand case study. J. Am. Med. Inf. Assoc. (JAMIA) 15(5), 701–704 (2008)CrossRefGoogle Scholar
  3. 3.
    S.L. Caudle, W.L.R. Gorr, K.E. Newcomer, Key information systems management issues for the public sector. MIS Q. 15(2), 171–188 (1991)CrossRefGoogle Scholar
  4. 4.
    M. Ward, S. Mitchell, A comparison of the strategic priorities of public and private sector information resource management executives. Gov. Inf. Q. 21(3), 284–304 (2004)CrossRefGoogle Scholar
  5. 5.
    MoSPI, Manual—infrastructure statistics CSO-MIS-2012 (Central Statistics Office and Programme Implementation Government of India, New Delhi, 2012)Google Scholar
  6. 6.
    M.N. Murty, K.K. Dhavala, R. Singh, Social cost-benefit analysis of Delhi (Report for Planning Commission, Government of India, Institute of Economic Growth, New Delhi, 2006)Google Scholar
  7. 7.
    F. Beckers, N. Chiara, A. Flesch, J. Maly, E. Silva, U. Stegemann, A risk-management approach to a successful infrastructure project. Mckinsey Working Paper on Risk. (52), 18 (2013)Google Scholar
  8. 8.
    M. Sambasivan, Y.W. Soon, Causes and effects of delays in Malaysian construction industry. Int. J. Proj. Manag. 25(5), 517–526 (2007)CrossRefGoogle Scholar
  9. 9.
    S.O. Babatunde, A. Opawole, I.C. Ujaddughe, An appraisal of project procurement methods in the Nigerian construction industry. Civ. Eng. Dimens. 12(1), 1–7 (2010)Google Scholar
  10. 10.
    O. Motaleb, M. Kishk, An investigation into causes and effects of construction delays in UAE, in Annual Conference of the Association of Researchers in Construction Management (2010), p. 26Google Scholar
  11. 11.
    A.A. Aibinu, G.O. Jagboro, The effects of construction delays on project delivery in Nigerian construction industry. Int. J. Proj. Manag. 20(8), 593–599 (2012)CrossRefGoogle Scholar
  12. 12.
    J.K. Lee, Cost overrun and cause in Korean social overhead capital projects: roads, rails, airports, and ports. J. Urb. Plan. Dev. 134(2), 59–62 (2008)CrossRefGoogle Scholar
  13. 13.
    B. Flyvbjerg, M.K.S. Holm, S.L. Buhl, What causes cost overrun in transport infrastructure projects? Transp. Rev. 24(1), 3–18 (2004)CrossRefGoogle Scholar
  14. 14.
    B. Flvbjerg, M.K.S. Holm, S.L. Buhl, How common and how large are cost overruns in transport infrastructure projects? Transp. Rev. 23(1), 71–88 (2003)CrossRefGoogle Scholar
  15. 15.
    C.N. Doll, O. Balaban, A methodology for evaluating environmental co-benefits in the transport sector: application to the Delhi Metro. J. Clean. Prod. 58, 61–73 (2013)CrossRefGoogle Scholar
  16. 16.
    N. Sharma, A. Singh, R. Dhyani, S. Gaur, Emission reduction from MRTS projects—a case study of Delhi metro. Atmos. Pollut. Res. 5(4), 721–728 (2014)CrossRefGoogle Scholar
  17. 17.
    S.K. Jain, K. Varun, N. Ramakrishna, Economic analysis of Hyderabad metro rail project. Int. J. Technol. 5(2), 297–303 (2015)CrossRefGoogle Scholar
  18. 18.
    D. Namiot, Z. Kutuzmanov, E. Fedorov, O. Pokusaev, On the assessment of socio-economic effects of the city railway. Int. J. Open Inf. 6, 92–103 (2018)Google Scholar
  19. 19.
    RITES, Integrated Multi-Modal Mass Rapid Transport System for Delhi: Economic Analysis for Modified First Phase (RITES, Gurgaon, 1995)Google Scholar
  20. 20.
    H. Bailly, P. Brinckerhoff, California life-cycle benefit/cost analysis model (Cal-B/C). (California Department of Transportation California, 1999)Google Scholar
  21. 21.
    T. Litman, ‘Vehicle Costs’-Transportation Cost and Benefit Analysis: Techniques and Implications (Victoria Transport Policy Institute, Victoria, 2009)Google Scholar
  22. 22.
    S. Polzin, X. Chu, S.R. Vishaka, Exploration of a Shift in Household Transportation Spending from Vehicles for Public Transportation (Centre for Urban Transportation Research- University of South Florida, Florida, 2008)Google Scholar
  23. 23.
    L.R. Kadiyali, Study for updating road user cost data, in Journal of Indian Roads Congress (1992)Google Scholar
  24. 24.
    A.K. Garg, S. Arya, The opportunity analysis of carbon credit trading for developing world—a case study. Int. J. Mark. Financ. Serv. Manag. Res. 4(2), 29–38 (2015)Google Scholar
  25. 25.
    MoSPI, 390th Flash Report on Central Sector Projects (Ministry of Statistics and Programme Implementation-Government of India, New Delhi, 2018)Google Scholar
  26. 26.
    E. Kula, Estimation of social rate of interest for India. J. Agric. Econ. 55(1), 91–99 (2004)CrossRefGoogle Scholar

Copyright information

© The Institution of Engineers (India) 2019

Authors and Affiliations

  • Yash Kumar Mittal
    • 1
    Email author
  • Virendra Kumar Paul
    • 1
  • Anil Sawhney
    • 2
  1. 1.Department of Building Engineering and ManagementSchool of Planning and Architecture DelhiNew DelhiIndia
  2. 2.Department of Built Environment, Faculty of Engineering and TechnologyLiverpool John Moores UniversityLiverpoolUK

Personalised recommendations